St Louis County Public Works Department

Welcome, Guest!
Log in | Employee Login | License
 

Bid Abstract

CP 0280-153456 TST - CP 0280-153456 TST (Tied) - Reclaim & OverlayUlland Brothers, Inc. Hawkinson Construction Co., Inc KGM Contractors, Inc Northland Constructors of Duluth, Inc. Hardrives, Inc (R) 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$6,460.00$6,460.00$20,000.00$20,000.00$15,000.00$15,000.00$5,000.00$5,000.00$400,000.00$400,000.00
2021.601MOBILIZATION, SEAL COATLUMP SUM1$850.00$850.00$1,000.00$1,000.00$1,500.00$1,500.00$1,050.00$1,050.00$5,000.00$5,000.00
2104.501REMOVE PIPE CULVERTSLIN FT175$14.00$2,450.00$12.60$2,205.00$15.00$2,625.00$26.00$4,550.00$5.00$875.00
2104.505REMOVE BITUMINOUS PAVEMENTSQ YD1,873$5.50$10,301.50$3.30$6,180.90$3.40$6,368.20$4.00$7,492.00$5.00$9,365.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)LIN FT670$2.00$1,340.00$1.95$1,306.50$2.25$1,507.50$2.00$1,340.00$5.00$3,350.00
2105.602TEMPORARY STREAM DIVERSION SYSTEMEACH1$7,200.00$7,200.00$3,352.00$3,352.00$5,500.00$5,500.00$3,500.00$3,500.00$5.00$5.00
2105.604GEOTEXTILE FABRIC TYPE VISQ YD627$4.00$2,508.00$2.25$1,410.75$3.35$2,100.45$3.00$1,881.00$1.00$627.00
2105.604GEOGRIDSQ YD225$5.00$1,125.00$2.40$540.00$5.00$1,125.00$3.40$765.00$1.00$225.00
2118.501AGGREGATE SURFACING CLASS 5TON1,809$15.00$27,135.00$17.00$30,753.00$13.50$24,421.50$20.00$36,180.00$25.00$45,225.00
2123.503MOTOR GRADERHOUR38$315.00$11,970.00$180.00$6,840.00$175.00$6,650.00$275.00$10,450.00$100.00$3,800.00
2123.5070.5 CU YD SHOVELHOUR38$260.00$9,880.00$174.00$6,612.00$145.00$5,510.00$260.00$9,880.00$100.00$3,800.00
2123.5258 TON STEEL-WHEELED ROLLERHOUR38$300.00$11,400.00$180.00$6,840.00$145.00$5,510.00$185.00$7,030.00$100.00$3,800.00
2130.501WATERM GALLON75$40.00$3,000.00$45.00$3,375.00$33.00$2,475.00$47.00$3,525.00$60.00$4,500.00
2131.502CALCIUM CHLORIDE SOLUTIONGALLON4,157$1.10$4,572.70$1.05$4,364.85$1.10$4,572.70$1.15$4,780.55$1.00$4,157.00
2211.501AGGREGATE BASE CLASS 5TON7,236$8.00$57,888.00$11.80$85,384.80$9.40$68,018.40$17.00$123,012.00$15.00$108,540.00
2211.503AGGREGATE BASE (CV) CLASS 5 (P)CU YD259$34.00$8,806.00$31.00$8,029.00$25.00$6,475.00$30.00$7,770.00$30.00$7,770.00
2211.604AGGREGATE BASE STABILIZATIONSQ YD36,022$0.50$18,011.00$0.64$23,054.08$0.61$21,973.42$0.47$16,930.34$1.00$36,022.00
2215.501FULL DEPTH RECLAMATIONSQ YD37,329$0.36$13,438.44$0.54$20,157.66$0.55$20,530.95$0.40$14,931.60$1.00$37,329.00
2355.502BITUMINOUS MATERIAL FOR FOG SEALGALLON3,658$4.00$14,632.00$3.75$13,717.50$3.95$14,449.10$3.90$14,266.20$2.00$7,316.00
2356.505BITUMINOUS MATERIAL FOR SEAL COATGALLON9,144$3.00$27,432.00$2.85$26,060.40$2.99$27,340.56$3.00$27,432.00$2.00$18,288.00
2356.506BITUMINOUS SEAL COATSQ YD27,709$0.50$13,854.50$0.45$12,469.05$0.47$13,023.23$0.47$13,023.23$2.00$55,418.00
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLON2,148$2.00$4,296.00$2.00$4,296.00$2.40$5,155.20$2.40$5,155.20$2.00$4,296.00
2357.606BITUMINOUS MATERIAL FOR SHOULDER TACKGALLON2,116$2.00$4,232.00$2.50$5,290.00$2.50$5,290.00$2.60$5,501.60$2.00$4,232.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (3,C)TON7,112$39.00$277,368.00$42.00$298,704.00$44.90$319,328.80$42.00$298,704.00$52.00$369,824.00
2360.505TYPE SP 12.5 BITUMINOUS MIXTURE FOR ENTRANCES (3,C)TON258$57.50$14,835.00$72.00$18,576.00$70.00$18,060.00$75.00$19,350.00$80.00$20,640.00
2412.5117X3 PRECAST CONCRETE BOX CULVERTLIN FT44$525.00$23,100.00$213.00$9,372.00$675.00$29,700.00$510.00$22,440.00$500.00$22,000.00
2412.5127X3 PRECAST CONCRETE BOX CULVERT END SECTIONEACH2$4,800.00$9,600.00$1,990.50$3,981.00$5,650.00$11,300.00$4,500.00$9,000.00$500.00$1,000.00
2451.501STRUCTURE EXCAVATION CLASS E (P)CU YD919$12.00$11,028.00$17.45$16,036.55$11.55$10,614.45$12.00$11,028.00$10.00$9,190.00
2451.503GRANULAR BACKFILL (CV) (P)CU YD536$22.00$11,792.00$25.65$13,748.40$14.45$7,745.20$29.00$15,544.00$5.00$2,680.00
2451.507GRANULAR BEDDING (CV) (P)CU YD46$33.00$1,518.00$39.05$1,796.30$31.00$1,426.00$41.00$1,886.00$5.00$230.00
2501.51118" RC PIPE CULVERTLIN FT68$36.00$2,448.00$61.85$4,205.80$70.00$4,760.00$49.00$3,332.00$50.00$3,400.00
2501.51518" RC PIPE APRONEACH4$900.00$3,600.00$559.00$2,236.00$550.00$2,200.00$670.00$2,680.00$500.00$2,000.00
2540.602MAIL BOX SUPPORTEACH42$130.00$5,460.00$125.00$5,250.00$135.00$5,670.00$130.00$5,460.00$150.00$6,300.00
2563.601TRAFFIC CONTROLLUMP SUM1$5,500.00$5,500.00$8,300.00$8,300.00$6,500.00$6,500.00$10,500.00$10,500.00$10,000.00$10,000.00
2563.601TRAFFIC CONTROL, SEAL COATLUMP SUM1$510.00$510.00$500.00$500.00$525.00$525.00$600.00$600.00$5,000.00$5,000.00
2573.533SEDIMENT CONTROL LOG TYPE STRAWLIN FT576$5.00$2,880.00$4.25$2,448.00$6.60$3,801.60$3.40$1,958.40$1.25$720.00
2575.572RAPID STABILIZATION METHOD 4SQ YD498$2.00$996.00$1.55$771.90$4.28$2,131.44$1.60$796.80$5.00$2,490.00
2580.603INTERIM PAVEMENT MARKINGLIN FT29,758$0.15$4,463.70$0.20$5,951.60$0.10$2,975.80$0.09$2,678.22$0.30$8,927.40
2580.603INTERIM PAVEMENT MARKINGLIN FT29,758$0.12$3,570.96$0.15$4,463.70$0.10$2,975.80$0.13$3,868.54$0.30$8,927.40
2582.5026" SOLID LINE WHITE-EPOXYLIN FT24,448$0.30$7,334.40$0.26$6,356.48$0.08$1,955.84$0.28$6,845.44$0.10$2,444.80
2582.5024" BROKEN LINE YELLOW-EPOXYLIN FT1,930$0.20$386.00$0.20$386.00$0.05$96.50$0.20$386.00$0.10$193.00
2582.5024" SOLID LINE YELLOW-PAINTLIN FT6,917$0.05$345.85$0.05$345.85$0.05$345.85$0.06$415.02$0.10$691.70
2582.5024" DOUBLE SOLID LINE YELLOW-PAINTLIN FT3,016$0.10$301.60$0.10$301.60$0.11$331.76$0.13$392.08$0.20$603.20
2582.5024" SOLID LINE YELLOW-EPOXYLIN FT6,917$0.20$1,383.40$0.20$1,383.40$0.05$345.85$0.20$1,383.40$0.10$691.70
2582.50224" SOLID LINE WHITE-PAINTLIN FT40$3.37$134.80$3.30$132.00$3.50$140.00$4.10$164.00$0.10$4.00
2582.5026" SOLID LINE WHITE-PAINTLIN FT24,448$0.08$1,955.84$0.08$1,955.84$0.08$1,955.84$0.09$2,200.32$0.10$2,444.80
2582.5024" DOUBLE SOLID LINE YELLOW-EPOXYLIN FT3,016$0.50$1,508.00$0.40$1,206.40$0.11$331.76$0.40$1,206.40$0.20$603.20
2582.5024" BROKEN LINE YELLOW-PAINTLIN FT1,930$0.05$96.50$0.05$96.50$0.05$96.50$0.06$115.80$0.10$193.00
2582.50224" SOLID LINE WHITE-EPOXYLIN FT40$7.50$300.00$7.00$280.00$3.47$138.80$9.20$368.00$0.10$4.00
 Totals for project CP 0280-153456 TST $655,198.19 $702,023.81 $702,574.00 $748,748.14 $1,245,142.20
 
Contract Total:$655,198.19$702,023.81$702,574.00$748,748.14$1,245,142.20