CP 0035-244410 TST - CP 0035-244410 TST - Reclaim/Overlay & CulvertsKGM Contractors, Inc Ulland Brothers, Inc. Northland Constructors of Duluth, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$55,500.00$55,500.00$47,310.00$47,310.00$8,000.00$8,000.00
2021.601MOBILIZATION, SEAL COATLUMP SUM1$4,500.00$4,500.00$200.00$200.00$4,200.00$4,200.00
2104.501REMOVE PIPE CULVERTSLIN FT599$10.00$5,990.00$9.00$5,391.00$15.00$8,985.00
2104.505REMOVE BITUMINOUS PAVEMENTSQ YD2,645$3.00$7,935.00$3.50$9,257.50$2.50$6,612.50
2104.513SAWING BIT PAVEMENT (FULL DEPTH)LIN FT1,004$1.65$1,656.60$2.00$2,008.00$1.94$1,947.76
2105.604GEOGRIDSQ YD886$4.90$4,341.40$3.50$3,101.00$4.00$3,544.00
2105.604GEOTEXTILE FABRIC TYPE VISQ YD2,047$3.05$6,243.35$2.50$5,117.50$2.00$4,094.00
2118.501AGGREGATE SURFACING CLASS 5TON1,745$15.70$27,396.50$17.96$31,340.20$14.50$25,302.50
2123.503MOTOR GRADERHOUR40$185.00$7,400.00$290.00$11,600.00$250.00$10,000.00
2123.5070.5 CU YD SHOVELHOUR16$178.00$2,848.00$380.00$6,080.00$250.00$4,000.00
2123.5258 TON STEEL-WHEELED ROLLERHOUR40$135.00$5,400.00$290.00$11,600.00$185.00$7,400.00
2130.501WATERM GALLON90$30.00$2,700.00$53.00$4,770.00$50.00$4,500.00
2131.502CALCIUM CHLORIDE SOLUTIONGALLON10,470$1.15$12,040.50$1.15$12,040.50$1.15$12,040.50
2211.501AGGREGATE BASE CLASS 5TON10,903$9.35$101,943.05$9.65$105,213.95$13.80$150,461.40
2211.503AGGREGATE BASE (CV) CLASS 5 (P)CU YD754$19.50$14,703.00$24.00$18,096.00$27.00$20,358.00
2215.501FULL DEPTH RECLAMATIONSQ YD46,456$0.56$26,015.36$0.36$16,724.16$0.44$20,440.64
2215.604BASE STABILIZATION (BASE ONE)SQ YD47,112$0.60$28,267.20$0.40$18,844.80$0.46$21,671.52
2355.502BITUMINOUS MATERIAL FOR FOG SEALGALLON4,816$4.00$19,264.00$3.85$18,541.60$3.90$18,782.40
2356.505BITUMINOUS MATERIAL FOR SEAL COATGALLON12,438$2.95$36,692.10$2.80$34,826.40$2.90$36,070.20
2356.506BITUMINOUS SEAL COATSQ YD37,690$0.51$19,221.90$0.49$18,468.10$0.50$18,845.00
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLON2,591$2.40$6,218.40$2.00$5,182.00$2.20$5,700.20
2357.606BITUMINOUS MATERIAL FOR SHOULDER TACKGALLON2,254$2.45$5,522.30$2.00$4,508.00$2.90$6,536.60
2360.501TYPE SP 9.5 WEARING COURSE MIX (3,C)TON8,682$46.95$407,619.90$46.25$401,542.50$48.00$416,736.00
2360.505TYPE SP 9.5 BIT MIXTURE FOR ENTRANCES (3,C)TON77$70.00$5,390.00$160.00$12,320.00$98.00$7,546.00
2451.501STRUCTURE EXCAVATION CLASS E (P)CU YD2,703$10.75$29,057.25$12.50$33,787.50$8.00$21,624.00
2451.503GRANULAR BACKFILL (CV) (P)CU YD1,455$13.50$19,642.50$24.50$35,647.50$24.00$34,920.00
2451.507GRANULAR BEDDING (P)CU YD214$25.00$5,350.00$33.00$7,062.00$34.00$7,276.00
2501.51524" RC PIPE APRONEACH4$585.00$2,340.00$750.00$3,000.00$650.00$2,600.00
2501.52122" SPAN RC PIPE-ARCH CULV CL IIALIN FT214$73.00$15,622.00$66.00$14,124.00$58.00$12,412.00
2501.52128" SPAN RC PIPE-ARCH CULV CL IIALIN FT150$90.00$13,500.00$84.00$12,600.00$73.00$10,950.00
2501.52144" SPAN RC PIPE-ARCH CULV CL IIALIN FT72$160.00$11,520.00$92.00$6,624.00$120.00$8,640.00
2501.52544" SPAN RC PIPE-ARCH APRONEACH4$1,450.00$5,800.00$1,400.00$5,600.00$1,500.00$6,000.00
2501.52528" SPAN RC PIPE-ARCH APRONEACH8$585.00$4,680.00$1,200.00$9,600.00$660.00$5,280.00
2501.52522" SPAN RC PIPE-ARCH APRONEACH12$450.00$5,400.00$850.00$10,200.00$580.00$6,960.00
2501.56124" RC PIPE CULVERT DES 3006LIN FT78$60.00$4,680.00$36.00$2,808.00$57.00$4,446.00
2540.602MAIL BOX SUPPORTEACH42$135.00$5,670.00$134.02$5,628.84$125.00$5,250.00
2563.601TRAFFIC CONTROLLUMP SUM1$4,500.00$4,500.00$6,936.00$6,936.00$10,000.00$10,000.00
2563.601TRAFFIC CONTROL, SEAL COATLUMP SUM1$2,000.00$2,000.00$500.00$500.00$525.00$525.00
2563.601WORK ZONE SPEED LIMITLUMP SUM1$600.00$600.00$102.00$102.00$105.00$105.00
2573.533SEDIMENT CONTROL LOG TYPE STRAWLIN FT1,592$3.40$5,412.80$3.75$5,970.00$3.90$6,208.80
2575.572RAPID STABILIZATION METHOD 4SQ YD1,822$1.90$3,461.80$1.90$3,461.80$2.00$3,644.00
2580.603INTERIM PAVEMENT MARKINGLIN FT39,686$0.12$4,762.32$0.11$4,365.46$0.11$4,365.46
2580.603INTERIM PAVEMENT MARKINGLIN FT39,686$0.11$4,365.46$0.11$4,365.46$0.11$4,365.46
2582.5024" DBLE SOLID LINE EPOXYLIN FT6,875$0.50$3,437.50$0.48$3,300.00$0.48$3,300.00
2582.5024" SOLID LINE PAINTLIN FT4,353$0.10$435.30$0.10$435.30$0.06$261.18
2582.50224" SOLID LINE PAINTLIN FT60$3.15$189.00$3.06$183.60$5.80$348.00
2582.5024" DBLE SOLID LINE PAINTLIN FT6,875$0.20$1,375.00$0.19$1,306.25$0.13$893.75
2582.50224" SOLID LINE EPOXYLIN FT60$7.35$441.00$7.14$428.40$8.90$534.00
2582.5024" BROKEN LINE PAINTLIN FT1,740$0.10$174.00$0.10$174.00$0.06$104.40
2582.5024" BROKEN LINE EPOXYLIN FT1,740$0.25$435.00$0.24$417.60$0.24$417.60
2582.5026" SOLID LINE EPOXYLIN FT31,247$0.32$9,999.04$0.31$9,686.57$0.29$9,061.63
2582.5024" SOLID LINE EPOXYLIN FT4,353$0.25$1,088.25$0.24$1,044.72$0.24$1,044.72
2582.5026" SOLID LINE PAINTLIN FT31,247$0.12$3,749.64$0.11$3,437.17$0.10$3,124.70
 Totals for project CP 0035-244410 TST $984,496.42 $996,879.38 $998,435.92
 
Contract Total:$984,496.42$996,879.38$998,435.92