St Louis County Public Works Department

Welcome, Guest!
Log in | Employee Login | License
 

Bid Abstract

CP 0223-244397 TST - CP 0223-244397 TST (Low) - Reclaim & Overlay/CulvertsHawkinson Construction Co., Inc Ulland Brothers, Inc. KGM Contractors, Inc Northland Constructors of Duluth, Inc. Hardrives, Inc (R) 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$39,000.00$39,000.00$25,740.00$25,740.00$55,000.00$55,000.00$10,000.00$10,000.00$32,000.00$32,000.00
2021.601MOBILIZATION, SEAL COATLUMP SUM1$2,000.00$2,000.00$2,000.00$2,000.00$2,500.00$2,500.00$2,100.00$2,100.00$15,000.00$15,000.00
2021.601RAILROAD PROTECTIVE SERVICESLUMP SUM1$6,900.00$6,900.00$5,000.00$5,000.00$11,500.00$11,500.00$5,500.00$5,500.00$5,500.00$5,500.00
2104.501REMOVE PIPE CULVERTSLIN FT578$11.00$6,358.00$11.00$6,358.00$10.00$5,780.00$22.00$12,716.00$15.00$8,670.00
2104.505REMOVE BITUMINOUS PAVEMENTSQ YD2,368$3.00$7,104.00$3.00$7,104.00$3.75$8,880.00$2.00$4,736.00$6.00$14,208.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)LIN FT1,306$1.50$1,959.00$1.50$1,959.00$2.75$3,591.50$1.40$1,828.40$1.40$1,828.40
2105.604GEOTEXTILE FABRIC TYPE VISQ YD2,520$3.00$7,560.00$3.00$7,560.00$3.05$7,686.00$2.40$6,048.00$2.00$5,040.00
2105.604GEOGRIDSQ YD1,050$3.50$3,675.00$3.50$3,675.00$4.90$5,145.00$3.00$3,150.00$3.00$3,150.00
2118.501AGGREGATE SURFACING CLASS 5TON1,516$15.40$23,346.40$20.00$30,320.00$15.60$23,649.60$25.00$37,900.00$19.00$28,804.00
2123.503MOTOR GRADERHOUR39$180.00$7,020.00$300.00$11,700.00$175.00$6,825.00$250.00$9,750.00$126.00$4,914.00
2123.5070.5 CU YD SHOVELHOUR20$300.00$6,000.00$300.00$6,000.00$250.00$5,000.00$285.00$5,700.00$175.00$3,500.00
2123.5258 TON STEEL-WHEELED ROLLERHOUR39$180.00$7,020.00$300.00$11,700.00$145.00$5,655.00$185.00$7,215.00$107.00$4,173.00
2130.501WATERM GALLON100$45.00$4,500.00$50.00$5,000.00$29.00$2,900.00$46.00$4,600.00$60.00$6,000.00
2131.502CALCIUM CHLORIDE SOLUTIONGALLON6,053$1.10$6,658.30$1.10$6,658.30$1.10$6,658.30$1.10$6,658.30$1.35$8,171.55
2211.501AGGREGATE BASE CLASS 5TON2,690$10.30$27,707.00$9.50$25,555.00$12.30$33,087.00$15.00$40,350.00$10.50$28,245.00
2211.503AGGREGATE BASE (CV) CLASS 5 (P)CU YD421$26.00$10,946.00$26.00$10,946.00$21.50$9,051.50$30.00$12,630.00$33.00$13,893.00
2211.604AGGREGATE BASE STABILIZATIONSQ YD44,968$0.67$30,128.56$0.40$17,987.20$0.58$26,081.44$0.40$17,987.20$0.50$22,484.00
2215.501FULL DEPTH RECLAMATIONSQ YD49,408$0.54$26,680.32$0.40$19,763.20$0.56$27,668.48$0.41$20,257.28$0.47$23,221.76
2355.502BITUMINOUS MATERIAL FOR FOG SEALGALLON4,982$3.50$17,437.00$3.50$17,437.00$3.68$18,333.76$3.65$18,184.30$2.53$12,604.46
2356.505BITUMINOUS MATERIAL FOR SEAL COATGALLON12,898$3.00$38,694.00$3.00$38,694.00$3.15$40,628.70$3.10$39,983.80$2.53$32,631.94
2356.506BITUMINOUS SEAL COATSQ YD39,084$0.45$17,587.80$0.45$17,587.80$0.47$18,369.48$0.47$18,369.48$0.69$26,967.96
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLON2,755$1.80$4,959.00$2.00$5,510.00$2.25$6,198.75$2.20$6,061.00$1.30$3,581.50
2357.606BITUMINOUS MATERIAL FOR SHOULDER TACKGALLON1,280$2.20$2,816.00$2.00$2,560.00$2.40$3,072.00$2.60$3,328.00$2.50$3,200.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (3,C)TON9,440$37.40$353,056.00$39.70$374,768.00$39.00$368,160.00$40.00$377,600.00$44.30$418,192.00
2360.505TYPE SP 12.5 BITUMINOUS MIXTURE FOR ENTRANCES (3,C)TON63$76.00$4,788.00$150.00$9,450.00$70.00$4,410.00$100.00$6,300.00$91.00$5,733.00
2451.501STRUCTURE EXCAVATION CLASS E (P)CU YD2,364$12.00$28,368.00$12.00$28,368.00$11.25$26,595.00$13.00$30,732.00$10.00$23,640.00
2451.503GRANULAR BACKFILL (CV) (P)CU YD1,793$18.00$32,274.00$18.00$32,274.00$14.75$26,446.75$26.00$46,618.00$25.00$44,825.00
2451.507GRANULAR BEDDING (CV) (P)CU YD180$15.00$2,700.00$15.00$2,700.00$25.00$4,500.00$35.00$6,300.00$25.00$4,500.00
2501.51518" RC PIPE APRONEACH8$400.00$3,200.00$400.00$3,200.00$550.00$4,400.00$650.00$5,200.00$635.00$5,080.00
2501.52122" SPAN RC PIPE-ARCH CULV CL IIALIN FT324$52.00$16,848.00$52.00$16,848.00$80.00$25,920.00$70.00$22,680.00$100.00$32,400.00
2501.52522" SPAN RC PIPE-ARCH APRONEACH20$400.00$8,000.00$400.00$8,000.00$550.00$11,000.00$650.00$13,000.00$627.00$12,540.00
2501.56118" RC PIPE CULVERT DES 3006LIN FT152$37.00$5,624.00$37.00$5,624.00$60.00$9,120.00$60.00$9,120.00$71.50$10,868.00
2540.602MAIL BOX SUPPORTEACH42$130.00$5,460.00$130.00$5,460.00$136.50$5,733.00$135.00$5,670.00$131.00$5,502.00
2563.601TRAFFIC CONTROL, SEAL COATLUMP SUM1$400.00$400.00$400.00$400.00$1,000.00$1,000.00$1,100.00$1,100.00$400.00$400.00
2563.601TRAFFIC CONTROLLUMP SUM1$6,000.00$6,000.00$4,900.00$4,900.00$5,300.00$5,300.00$21,700.00$21,700.00$4,900.00$4,900.00
2563.601WORK ZONE SPEED LIMITLUMP SUM1$600.00$600.00$600.00$600.00$1,200.00$1,200.00$450.00$450.00$600.00$600.00
2573.533SEDIMENT CONTROL LOG TYPE STRAWLIN FT2,163$3.00$6,489.00$3.00$6,489.00$4.44$9,603.72$3.10$6,705.30$3.00$6,489.00
2575.572RAPID STABILIZATION METHOD 4SQ YD1,566$1.80$2,818.80$1.80$2,818.80$2.22$3,476.52$1.90$2,975.40$1.60$2,505.60
2580.603INTERIM PAVEMENT MARKINGLIN FT48,432$0.10$4,843.20$0.11$5,327.52$0.10$4,843.20$0.17$8,233.44$0.16$7,749.12
2580.603INTERIM PAVEMENT MARKINGLIN FT48,432$0.20$9,686.40$0.11$5,327.52$0.10$4,843.20$0.17$8,233.44$0.10$4,843.20
2582.501PAVT MSSG (RR XING) PAINTEACH2$150.00$300.00$150.00$300.00$157.50$315.00$152.00$304.00$227.73$455.46
2582.501PAVT MSSG (RR XING) EPOXYEACH2$650.00$1,300.00$650.00$1,300.00$682.50$1,365.00$660.00$1,320.00$581.98$1,163.96
2582.50224" SOLID LINE WHITE-PAINTLIN FT172$2.80$481.60$2.80$481.60$2.94$505.68$2.85$490.20$4.05$696.60
2582.5026" SOLID LINE WHITE-PAINTLIN FT30,424$0.08$2,433.92$0.07$2,129.68$0.08$2,433.92$0.08$2,433.92$0.07$2,129.68
2582.5024" SOLID LINE YELLOW-PAINTLIN FT5,310$0.06$318.60$0.06$318.60$0.06$318.60$0.06$318.60$0.05$265.50
2582.5024" BROKEN LINE YELLOW-PAINTLIN FT1,360$0.06$81.60$0.06$81.60$0.06$81.60$0.06$81.60$0.05$68.00
2582.5024" DOUBLE SOLID LINE YELLOW-PAINTLIN FT8,773$0.12$1,052.76$0.12$1,052.76$0.13$1,140.49$0.13$1,140.49$0.10$877.30
2582.50224" SOLID LINE WHITE-EPOXYLIN FT172$7.00$1,204.00$7.00$1,204.00$7.35$1,264.20$7.20$1,238.40$7.09$1,219.48
2582.5026" SOLID LINE WHITE-EPOXYLIN FT30,424$0.25$7,606.00$0.25$7,606.00$0.27$8,214.48$0.26$7,910.24$0.28$8,518.72
2582.5024" SOLID LINE YELLOW-EPOXYLIN FT5,310$0.20$1,062.00$0.20$1,062.00$0.21$1,115.10$0.21$1,115.10$0.21$1,115.10
2582.5024" BROKEN LINE YELLOW-EPOXYLIN FT1,360$0.20$272.00$0.20$272.00$0.21$285.60$0.21$285.60$0.21$285.60
2582.5024" DOUBLE SOLID LINE YELLOW-EPOXYLIN FT8,773$0.40$3,509.20$0.40$3,509.20$0.42$3,684.66$0.41$3,596.93$0.43$3,772.39
 Totals for project CP 0223-244397 TST $816,833.46 $818,686.78 $870,537.23 $887,905.42 $919,123.28
 
Contract Total:$816,833.46$818,686.78$870,537.23$887,905.42$919,123.28