St Louis County Public Works Department

Welcome, Guest!
Log in | Employee Login | License
 

Bid Abstract

CP 176330 - SAP 69-710-025 Br 488 ReconstructionNorthland Constructors of Duluth, Inc. Redstone Construction, LLC - OLD KGM Contractors, Inc Zenith Tech, Inc Robert R. Schroeder Const., Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$142,000.00$142,000.00$264,500.00$264,500.00$238,000.00$238,000.00$355,000.00$355,000.00$367,718.00$367,718.00
2031.501FIELD OFFICE TYPE DEACH1$10,500.00$10,500.00$10,500.00$10,500.00$10,000.00$10,000.00$10,000.00$10,000.00$5,000.00$5,000.00
2101.511CLEARING & GRUBBINGLUMP SUM1$45,200.00$45,200.00$45,000.00$45,000.00$45,000.00$45,000.00$30,000.00$30,000.00$30,000.00$30,000.00
2104.501REMOVE GUARDRAIL-PLATE BEAMLIN FT504$7.00$3,528.00$6.00$3,024.00$6.30$3,175.20$6.00$3,024.00$6.00$3,024.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)LIN FT97$2.00$194.00$3.75$363.75$3.75$363.75$5.00$485.00$1.75$169.75
2104.523SALVAGE SIGNEACH8$30.00$240.00$25.00$200.00$50.00$400.00$75.00$600.00$25.00$200.00
2105.601DEWATERINGLUMP SUM1$500.00$500.00$20,000.00$20,000.00$11,500.00$11,500.00$10,000.00$10,000.00$5,000.00$5,000.00
2105.604GEOTEXTILE FABRIC TYPE VISQ YD26,667$2.00$53,334.00$2.85$76,000.95$2.85$76,000.95$2.25$60,000.75$2.25$60,000.75
2106.607EXCAVATION - COMMON (P)CU YD41,859$10.00$418,590.00$8.35$349,522.65$8.35$349,522.65$9.00$376,731.00$9.00$376,731.00
2106.607SELECT GRANULAR EMBANKMENT MOD 7% (CV) (P)CU YD16,353$12.00$196,236.00$18.60$304,165.80$18.39$300,731.67$17.50$286,177.50$17.50$286,177.50
2106.607GRANULAR EMBANKMENT (CV) (P)CU YD4,038$12.00$48,456.00$15.45$62,387.10$15.43$62,306.34$12.00$48,456.00$12.00$48,456.00
2118.607AGGREGATE SURFACING (CV) CLASS 5 (P)CU YD56$38.00$2,128.00$50.00$2,800.00$50.00$2,800.00$35.00$1,960.00$35.00$1,960.00
2211.503AGGREGATE BASE (CV) CLASS 5 (P)CU YD4,486$25.00$112,150.00$19.00$85,234.00$19.00$85,234.00$24.00$107,664.00$24.00$107,664.00
2232.603MILLED RUMBLE STRIPSLIN FT6,639$1.08$7,170.12$1.05$6,970.95$1.25$8,298.75$1.03$6,838.17$1.03$6,838.17
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLON532$3.20$1,702.40$3.00$1,596.00$3.00$1,596.00$3.00$1,596.00$3.00$1,596.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (3,C)TON5,253$59.00$309,927.00$60.00$315,180.00$60.00$315,180.00$56.50$296,794.50$56.50$296,794.50
2401.501STRUCTURAL CONCRETE (3Y43) (P)CU YD263$900.00$236,700.00$575.00$151,225.00$605.00$159,115.00$750.00$197,250.00$625.00$164,375.00
2401.512BRIDGE SLAB CONCRETE (3Y33) (P)SQ FT7,515$22.00$165,330.00$16.50$123,997.50$17.35$130,385.25$27.75$208,541.25$23.00$172,845.00
2401.513TYPE P-2 (TL-4) RAILING CONCRETE (3Y46) (P)LIN FT366$63.00$23,058.00$85.00$31,110.00$89.25$32,665.50$125.00$45,750.00$85.00$31,110.00
2401.541REINFORCEMENT BARS (EPOXY COATED) (P)POUND81,630$1.37$111,833.10$1.25$102,037.50$1.30$106,119.00$1.22$99,588.60$1.40$114,282.00
2401.541REINFORCEMENT BARS (STAINLESS-60 KSI) (P)POUND580$5.00$2,900.00$5.00$2,900.00$5.25$3,045.00$4.25$2,465.00$5.00$2,900.00
2401.601SLOPE PREPARATIONLUMP SUM1$4,000.00$4,000.00$5,000.00$5,000.00$9,000.00$9,000.00$4,000.00$4,000.00$3,800.00$3,800.00
2401.601STRUCTURE EXCAVATIONLUMP SUM1$35,000.00$35,000.00$20,550.00$20,550.00$31,000.00$31,000.00$20,000.00$20,000.00$50,000.00$50,000.00
2401.601FOUNDATION PREP PILE BENT PIERSLUMP SUM1$148,500.00$148,500.00$100,000.00$100,000.00$105,000.00$105,000.00$115,000.00$115,000.00$80,000.00$80,000.00
2402.584STRUCTURAL TUBE RAILING DESIGN T-1 (P)LIN FT354$120.00$42,480.00$115.00$40,710.00$121.00$42,834.00$125.00$44,250.00$140.00$49,560.00
2402.590ELASTOMERIC BEARING PAD TYPE 1EACH10$200.00$2,000.00$100.00$1,000.00$105.00$1,050.00$125.00$1,250.00$150.00$1,500.00
2402.595BEARING ASSEMBLYEACH24$850.00$20,400.00$900.00$21,600.00$945.00$22,680.00$1,000.00$24,000.00$875.00$21,000.00
2404.501CONCRETE WEARING COURSE (3U17A) (P)SQ FT10,155$7.40$75,147.00$7.00$71,085.00$7.35$74,639.25$6.65$67,530.75$5.50$55,852.50
2405.502PRESTRESSED CONCRETE BEAMS 27M (P)LIN FT926$255.00$236,130.00$250.00$231,500.00$263.00$243,538.00$250.00$231,500.00$350.00$324,100.00
2406.553BRIDGE APPROACH PANELS (P)SQ YD369$195.00$71,955.00$180.00$66,420.00$189.00$69,741.00$185.00$68,265.00$200.00$73,800.00
2442.501REMOVE EXISTING BRIDGELUMP SUM1$58,000.00$58,000.00$50,000.00$50,000.00$52,500.00$52,500.00$75,000.00$75,000.00$80,000.00$80,000.00
2451.511COARSE FILTER AGGREGATE (CV)CU YD30$35.00$1,050.00$48.00$1,440.00$50.00$1,500.00$45.00$1,350.00$45.00$1,350.00
2452.510STEEL H-PILING DRIVEN 14"LIN FT800$1.00$800.00$1.00$800.00$1.05$840.00$22.50$18,000.00$7.00$5,600.00
2452.510STEEL H-PILING DRIVEN 12"LIN FT500$1.00$500.00$1.00$500.00$1.05$525.00$20.80$10,400.00$5.00$2,500.00
2452.511STEEL H-PILING DELIVERED 12"LIN FT500$40.00$20,000.00$24.50$12,250.00$25.75$12,875.00$30.00$15,000.00$28.00$14,000.00
2452.511STEEL H-PILING DELIVERED 14"LIN FT800$50.00$40,000.00$34.00$27,200.00$35.70$28,560.00$41.00$32,800.00$38.00$30,400.00
2452.520STEEL H-TEST PILE 60 FT LONG 12"EACH2$5,500.00$11,000.00$12,000.00$24,000.00$12,600.00$25,200.00$2,800.00$5,600.00$10,000.00$20,000.00
2452.520STEEL H-TEST PILE 60 FT LONG 14"EACH2$7,000.00$14,000.00$17,500.00$35,000.00$18,375.00$36,750.00$3,500.00$7,000.00$12,000.00$24,000.00
2452.530PILE TIP PROTECTION 14"EACH18$180.00$3,240.00$175.00$3,150.00$184.00$3,312.00$140.00$2,520.00$200.00$3,600.00
2452.530PILE TIP PROTECTION 12"EACH12$140.00$1,680.00$125.00$1,500.00$132.00$1,584.00$110.00$1,320.00$140.00$1,680.00
2501.51118" CS PIPE CULVERTLIN FT176$30.00$5,280.00$50.00$8,800.00$50.00$8,800.00$33.00$5,808.00$33.00$5,808.00
2501.51518" CS PIPE APRONEACH6$300.00$1,800.00$330.00$1,980.00$330.00$1,980.00$300.00$1,800.00$300.00$1,800.00
2502.502DRAINAGE SYSTEM TYPE (B910)LUMP SUM1$2,100.00$2,100.00$2,000.00$2,000.00$2,100.00$2,100.00$3,000.00$3,000.00$2,000.00$2,000.00
2511.501RANDOM RIPRAP CLASS IIICU YD450$45.00$20,250.00$35.00$15,750.00$40.00$18,000.00$70.00$31,500.00$75.00$33,750.00
2511.501RANDOM RIPRAP CLASS IIICU YD21$45.00$945.00$35.00$735.00$40.00$840.00$70.00$1,470.00$75.00$1,575.00
2511.515GEOTEXTILE FILTER TYPE VIISQ YD850$3.50$2,975.00$2.00$1,700.00$3.70$3,145.00$8.60$7,310.00$3.50$2,975.00
2511.515GEOTEXTILE FILTER TYPE IVSQ YD142$3.00$426.00$4.50$639.00$4.70$667.40$3.00$426.00$4.50$639.00
2554.501TRAFFIC BARRIER DESIGN B8307LIN FT140$22.00$3,080.00$21.00$2,940.00$22.05$3,087.00$21.00$2,940.00$21.00$2,940.00
2554.501TRAFFIC BARRIER DESIGN SPECIALLIN FT100$68.00$6,800.00$65.00$6,500.00$68.25$6,825.00$65.00$6,500.00$65.00$6,500.00
2554.523END TREATMENT TANGENT TERMINALEACH3$2,450.00$7,350.00$2,328.00$6,984.00$2,450.00$7,350.00$2,328.00$6,984.00$2,328.00$6,984.00
2563.601TRAFFIC CONTROLLUMP SUM1$23,000.00$23,000.00$17,300.00$17,300.00$5,250.00$5,250.00$10,500.00$10,500.00$7,500.00$7,500.00
2564.536INSTALL SIGN PANEL TYPE CEACH4$115.00$460.00$110.00$440.00$105.00$420.00$300.00$1,200.00$110.00$440.00
2573.502SILT FENCE, TYPE HILIN FT7,910$3.20$25,312.00$2.95$23,334.50$3.10$24,521.00$2.85$22,543.50$2.95$23,334.50
2573.505FLOTATION SILT CURTAIN TYPE MOVING WATERLIN FT435$20.00$8,700.00$18.05$7,851.75$18.95$8,243.25$25.00$10,875.00$18.05$7,851.75
2573.533SEDIMENT CONTROL LOG TYPE WOOD FIBERLIN FT360$3.60$1,296.00$3.45$1,242.00$3.65$1,314.00$4.50$1,620.00$3.45$1,242.00
2573.550EROSION CONTROL SUPERVISORLUMP SUM1$1,500.00$1,500.00$500.00$500.00$2,800.00$2,800.00$1,000.00$1,000.00$500.00$500.00
2573.602ROCK DITCH CHECKEACH10$200.00$2,000.00$1,000.00$10,000.00$1,000.00$10,000.00$300.00$3,000.00$300.00$3,000.00
2574.508FERTILIZER TYPE 3POUND2,625$0.65$1,706.25$0.63$1,653.75$0.66$1,732.50$0.60$1,575.00$0.63$1,653.75
2574.525COMMON TOPSOIL BORROWCU YD2,978$8.00$23,824.00$20.00$59,560.00$20.00$59,560.00$25.00$74,450.00$25.00$74,450.00
2575.501SEEDINGACRE7.5$84.00$630.00$80.00$600.00$84.00$630.00$150.00$1,125.00$80.00$600.00
2575.502SEED MIXTURE 36-311POUND252$27.00$6,804.00$25.75$6,489.00$27.00$6,804.00$32.00$8,064.00$25.75$6,489.00
2575.523EROSION CONTROL BLANKETS CATEGORY 5SQ YD1,761$1.70$2,993.70$1.60$2,817.60$1.70$2,993.70$2.85$5,018.85$1.59$2,799.99
2575.523EROSION CONTROL BLANKETS CATEGORY 3SQ YD31,143$1.10$34,257.30$1.00$31,143.00$1.05$32,700.15$1.30$40,485.90$1.01$31,454.43
2575.571RAPID STABILIZATION METHOD 3M GALLON8$950.00$7,600.00$900.00$7,200.00$945.00$7,560.00$980.00$7,840.00$900.00$7,200.00
2580.603INTERIM PAVEMENT MARKINGLIN FT2,020$0.67$1,353.40$1.00$2,020.00$0.22$444.40$1.00$2,020.00$1.00$2,020.00
2582.5024" SOLID LINE YELLOW-EPOXYLIN FT750$0.46$345.00$0.45$337.50$0.46$345.00$0.74$555.00$0.44$330.00
2582.5024" BROKEN LINE YELLOW-EPOXYLIN FT710$0.46$326.60$0.45$319.50$0.46$326.60$0.74$525.40$0.44$312.40
2582.5026" SOLID LINE WHITE-EPOXYLIN FT6,641$0.62$4,117.42$0.60$3,984.60$0.62$4,117.42$0.79$5,246.39$0.59$3,918.19
 Totals for project CP 176330 $2,874,790.29 $2,897,241.40 $2,927,123.73 $3,159,089.56 $3,165,651.18
 
Contract Total:$2,874,790.29$2,897,241.40$2,927,123.73$3,159,089.56$3,165,651.18