Contract Bid Abstract

CP 0128-414688 (Low) - CP 0128-414688 (Low), SAP 069-728-010 - CR 989 to TH 1/169KGM Contractors, Inc Mesabi Bituminous, Inc. Ulland Brothers, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2016.601QUALITY MANAGEMENTLUMP SUM1$2,400.00$2,400.00$2,500.00$2,500.00$3,800.00$3,800.00
2021.501MOBILIZATIONLUMP SUM1$102,000.00$102,000.00$35,000.00$35,000.00$30,500.00$30,500.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT214$3.60$770.40$3.00$642.00$2.00$428.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD3,156$3.65$11,519.40$3.80$11,992.80$7.00$22,092.00
2105.604GEOGRIDSQ YD2,167$4.00$8,668.00$2.50$5,417.50$2.50$5,417.50
2118.609RECYCLED AGGREGATE SURFACINGTON1,763$17.70$31,205.10$24.00$42,312.00$30.00$52,890.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR34$160.00$5,440.00$140.00$4,760.00$263.00$8,942.00
2123.5100.5 CU YD SHOVELHOUR10$175.00$1,750.00$150.00$1,500.00$172.00$1,720.00
2123.510MOTOR GRADERHOUR34$205.00$6,970.00$180.00$6,120.00$375.00$12,750.00
2130.523WATERM GALLON114$35.00$3,990.00$80.00$9,120.00$48.00$5,472.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON6,556$1.05$6,883.80$1.00$6,556.00$1.25$8,195.00
2211.509AGGREGATE BASE CLASS 5TON1,942$11.90$23,109.80$18.00$34,956.00$16.25$31,557.50
2215.504FULL DEPTH RECLAMATIONSQ YD33,450$0.55$18,397.50$0.66$22,077.00$0.50$16,725.00
2215.604BASE STABILIZATION (BASE ONE)SQ YD33,450$0.55$18,397.50$0.66$22,077.00$0.40$13,380.00
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON1,892$2.65$5,013.80$2.50$4,730.00$2.50$4,730.00
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON3,127$59.50$186,056.50$61.50$192,310.50$64.00$200,128.00
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON4,363$58.50$255,235.50$59.50$259,598.50$61.00$266,143.00
2540.602MAIL BOX SUPPORTEACH21$168.00$3,528.00$170.00$3,570.00$176.00$3,696.00
2554.603RAISE GUARDRAILLIN FT579$25.25$14,619.75$14.50$8,395.50$15.00$8,685.00
2563.601TRAFFIC CONTROLLUMP SUM1$4,500.00$4,500.00$2,400.00$2,400.00$5,280.00$5,280.00
2580.503INTERIM PAVEMENT MARKINGLIN FT20,070$0.15$3,010.50$0.36$7,225.20$0.25$5,017.50
2582.5034" DBLE SOLID LINE MULTI COMPLIN FT10,035$0.80$8,028.00$0.75$7,526.25$0.80$8,028.00
2582.5034" SOLID LINE MULTI COMPLIN FT19,892$0.40$7,956.80$0.38$7,558.96$0.40$7,956.80
2582.518PAVT MSSG PREF TAPE GR INSQ FT49.02$55.65$2,727.96$55.50$2,720.61$58.00$2,843.16
 Totals for project CP 0128-414688 (Low) $732,178.31 $701,065.82 $726,376.46
 
CP 0489-299096 (Tied) - CP 0489-299096 - CSAH 88 to End of BituminousKGM Contractors, Inc Mesabi Bituminous, Inc. Ulland Brothers, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$3,800.00$3,800.00$14,250.00$14,250.00$4,675.00$4,675.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT95$3.60$342.00$3.00$285.00$2.00$190.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD183$4.30$786.90$5.00$915.00$10.00$1,830.00
2118.509AGGREGATE SURFACING CLASS 5TON178$25.95$4,619.10$20.00$3,560.00$45.00$8,010.00
2123.510MOTOR GRADERHOUR8$205.00$1,640.00$180.00$1,440.00$375.00$3,000.00
2123.5100.5 CU YD SHOVELHOUR5$175.00$875.00$150.00$750.00$172.00$860.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR8$160.00$1,280.00$140.00$1,120.00$263.00$2,104.00
2130.523WATERM GALLON18$35.00$630.00$80.00$1,440.00$48.00$864.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON618$1.05$648.90$1.00$618.00$1.25$772.50
2211.509AGGREGATE BASE CLASS 5TON135$21.25$2,868.75$20.00$2,700.00$17.00$2,295.00
2215.504FULL DEPTH RECLAMATIONSQ YD3,016$0.60$1,809.60$1.95$5,881.20$0.50$1,508.00
2215.604BASE STABILIZATION (BASE ONE)SQ YD3,016$0.55$1,658.80$3.20$9,651.20$0.75$2,262.00
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON166$2.65$439.90$2.50$415.00$2.50$415.00
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON274$63.95$17,522.30$61.50$16,851.00$90.00$24,660.00
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON381$61.10$23,279.10$59.50$22,669.50$87.00$33,147.00
2563.601TRAFFIC CONTROLLUMP SUM1$4,500.00$4,500.00$2,300.00$2,300.00$3,190.00$3,190.00
2580.503INTERIM PAVEMENT MARKINGLIN FT1,464$0.15$219.60$0.52$761.28$0.25$366.00
2582.5034" DBLE SOLID LINE MULTI COMPLIN FT732$0.80$585.60$0.75$549.00$0.80$585.60
 Totals for project CP 0489-299096 (Tied) $67,505.55 $86,156.18 $90,734.10
 
CP 0989-299098 (Tied) - CP 0989-299098 - End of Bituminous to CSAH 128KGM Contractors, Inc Mesabi Bituminous, Inc. Ulland Brothers, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2016.601QUALITY MANAGEMENTLUMP SUM1$1,475.00$1,475.00$2,500.00$2,500.00$3,822.00$3,822.00
2021.501MOBILIZATIONLUMP SUM1$3,900.00$3,900.00$35,000.00$35,000.00$22,000.00$22,000.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT150$3.60$540.00$3.00$450.00$2.00$300.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD234$4.30$1,006.20$5.00$1,170.00$13.00$3,042.00
2105.604GEOGRIDSQ YD7,698$4.00$30,792.00$2.50$19,245.00$2.50$19,245.00
2118.609RECYCLED AGGREGATE SURFACINGTON980$15.85$15,533.00$24.00$23,520.00$31.00$30,380.00
2123.5100.5 CU YD SHOVELHOUR8$175.00$1,400.00$150.00$1,200.00$172.00$1,376.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR28$160.00$4,480.00$140.00$3,920.00$263.00$7,364.00
2123.510MOTOR GRADERHOUR28$205.00$5,740.00$180.00$5,040.00$375.00$10,500.00
2130.523WATERM GALLON94$35.00$3,290.00$80.00$7,520.00$48.00$4,512.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON4,405$1.05$4,625.25$1.00$4,405.00$1.25$5,506.25
2211.509AGGREGATE BASE CLASS 5TON4,478$11.35$50,825.30$20.00$89,560.00$16.50$73,887.00
2215.504FULL DEPTH RECLAMATIONSQ YD23,862$0.55$13,124.10$0.79$18,850.98$0.50$11,931.00
2215.604BASE STABILIZATION (BASE ONE)SQ YD23,862$0.60$14,317.20$0.69$16,464.78$0.50$11,931.00
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON1,111$2.65$2,944.15$2.50$2,777.50$2.50$2,777.50
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON1,903$61.60$117,224.80$61.50$117,034.50$61.00$116,083.00
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON2,633$59.90$157,716.70$59.50$156,663.50$59.00$155,347.00
2540.602MAIL BOX SUPPORTEACH24$168.00$4,032.00$170.00$4,080.00$176.00$4,224.00
2554.502END TREATMENT-ENERGY ABSORBING TERMINALEACH2$3,465.00$6,930.00$3,150.00$6,300.00$3,300.00$6,600.00
2554.503TRAFFIC BARRIER DESIGN B8307LIN FT280$37.95$10,626.00$20.00$5,600.00$21.00$5,880.00
2563.601TRAFFIC CONTROLLUMP SUM1$4,500.00$4,500.00$2,300.00$2,300.00$4,950.00$4,950.00
2580.503INTERIM PAVEMENT MARKINGLIN FT14,646$0.15$2,196.90$0.36$5,272.56$0.25$3,661.50
2582.5034" SOLID LINE MULTI COMPLIN FT1,352$0.40$540.80$0.38$513.76$0.40$540.80
2582.5034" DBLE SOLID LINE MULTI COMPLIN FT6,466$0.80$5,172.80$0.75$4,849.50$0.80$5,172.80
2582.5034" BROKEN LINE MULTI COMPLIN FT362$0.40$144.80$0.38$137.56$0.40$144.80
 Totals for project CP 0989-299098 (Tied) $463,077.00 $534,374.64 $511,177.65
 
Contract Total:$1,262,760.86$1,321,596.64$1,328,288.21