CP 0060-348247 (Low) - CP 0060-348247 (Low), SAP 069-660-011 - TH 73 to TH 169KGM Contractors, Inc Hawkinson Construction Co., Inc Ulland Brothers, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2016.601QUALITY MANAGEMENT SPECIALLUMP SUM1$1,500.00$1,500.00$1,730.00$1,730.00$1,400.00$1,400.00
2016.601QUALITY MANAGEMENTLUMP SUM1$1,500.00$1,500.00$1,730.00$1,730.00$1,400.00$1,400.00
2021.501MOBILIZATIONLUMP SUM1$59,000.00$59,000.00$64,350.00$64,350.00$20,607.53$20,607.53
2021.601RAILROAD PROTECTIVE SERVICESLUMP SUM1$7,500.00$7,500.00$7,950.00$7,950.00$11,900.00$11,900.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT483$4.50$2,173.50$1.75$845.25$2.00$966.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD1,073$3.50$3,755.50$6.94$7,446.62$5.79$6,212.67
2104.618REMOVE STONE PAVERSSQ FT214$2.60$556.40$3.37$721.18$2.00$428.00
2118.609RECYCLED AGGREGATE SURFACINGTON1,975$16.30$32,192.50$23.00$45,425.00$28.00$55,300.00
2123.510MOTOR GRADERHOUR48$205.00$9,840.00$190.00$9,120.00$380.00$18,240.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR48$160.00$7,680.00$190.00$9,120.00$250.00$12,000.00
2123.5100.5 CU YD SHOVELHOUR13$310.00$4,030.00$160.00$2,080.00$270.00$3,510.00
2130.523WATERM GALLON161$35.00$5,635.00$45.00$7,245.00$40.00$6,440.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON9,311$1.05$9,776.55$0.92$8,566.12$1.10$10,242.10
2211.509AGGREGATE BASE CLASS 5TON1,699$12.10$20,557.90$16.80$28,543.20$14.25$24,210.75
2215.504FULL DEPTH RECLAMATIONSQ YD49,567$0.58$28,748.86$0.73$36,183.91$0.40$19,826.80
2215.604BASE STABILIZATION (BASE ONE)SQ YD49,567$0.55$27,261.85$0.94$46,592.98$0.40$19,826.80
2221.509SHOULDER BASE AGGREGATE CLASS 5TON1,003$15.00$15,045.00$20.53$20,591.59$24.00$24,072.00
2232.504MILL BITUMINOUS SURFACE (2.0")SQ YD51,762$1.10$56,938.20$0.80$41,409.60$0.90$46,585.80
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON2,247$2.80$6,291.60$2.49$5,595.03$2.50$5,617.50
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON5,705$57.40$327,467.00$58.24$332,259.20$76.00$433,580.00
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON5,014$57.00$285,798.00$56.17$281,636.38$71.00$355,994.00
2540.602MAIL BOX SUPPORTEACH31$160.00$4,960.00$150.00$4,650.00$150.00$4,650.00
2563.601TRAFFIC CONTROLLUMP SUM1$5,100.00$5,100.00$12,300.00$12,300.00$4,242.00$4,242.00
2580.503INTERIM PAVEMENT MARKINGLIN FT12,760$0.15$1,914.00$0.12$1,531.20$0.24$3,062.40
2582.5034" DBLE SOLID LINE MULTI COMPLIN FT1,500$0.50$750.00$0.48$720.00$0.44$660.00
2582.50324" SOLID LINE PREF TAPE GR INLIN FT124$28.00$3,472.00$28.50$3,534.00$26.00$3,224.00
2582.5034" BROKEN LINE MULTI COMPLIN FT2,520$0.25$630.00$0.24$604.80$0.22$554.40
2582.5034" SOLID LINE MULTI COMPLIN FT7,240$0.25$1,810.00$0.24$1,737.60$0.22$1,592.80
2582.5036" SOLID LINE MULTI COMPLIN FT28,744$0.35$10,060.40$0.32$9,198.08$0.30$8,623.20
2582.518PAVT MSSG PREF TAPE GR INSQ FT123.44$45.00$5,554.80$45.00$5,554.80$42.00$5,184.48
 Totals for project CP 0060-348247 (Low) $947,499.06 $998,971.54 $1,110,153.23
 
Contract Total:$947,499.06$998,971.54$1,110,153.23