St Louis County Public Works Department

Welcome, Guest!
Log in | Employee Login | License
 

Info

The new site https://oneoffice.stlouiscountymn.gov/oneoffice should be used instead of this site. This site is only up for review purposes.

Bid Abstract

CP 0021-300205 (BR 285) - CP 0021-300205, SAP 069-621-036 (BR 285) - Bridge ConstructionRedstone Construction, LLC Northland Constructors of Duluth, Inc. S & R Reinforcing, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM0.45$240,000.00$108,000.00$215,608.34$97,023.75$187,960.00$84,582.00
2021.501MOBILIZATIONLUMP SUM0.55$240,000.00$132,000.00$215,608.34$118,584.59$187,960.00$103,378.00
2031.502FIELD OFFICE TYPE DEACH1$8,000.00$8,000.00$9,000.00$9,000.00$20,000.00$20,000.00
2101.501CLEARING & GRUBBINGLUMP SUM1$1,500.00$1,500.00$2,200.00$2,200.00$4,200.00$4,200.00
2104.502REMOVE MARKEREACH8$25.00$200.00$42.00$336.00$25.00$200.00
2104.502SALVAGE SIGNEACH3$25.00$75.00$42.00$126.00$25.00$75.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT100$5.00$500.00$2.00$200.00$4.25$425.00
2104.503REMOVE GUARDRAIL-PLATE BEAMLIN FT520$5.50$2,860.00$6.50$3,380.00$10.00$5,200.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD3,770$4.40$16,588.00$4.50$16,965.00$3.75$14,137.50
2104.601REMOVE REGULATED WASTE MATERIALLUMP SUM1$1.00$1.00$2,117.96$2,117.96$10,000.00$10,000.00
2105.601ONE LANE BYPASS (14' LANE)LUMP SUM1$200,000.00$200,000.00$240,000.00$240,000.00$246,380.00$246,380.00
2106.507EXCAVATION - COMMON (P)CU YD405$22.00$8,910.00$20.00$8,100.00$17.00$6,885.00
2106.507GRANULAR EMBANKMENT (CV) (P)CU YD35$15.50$542.50$37.00$1,295.00$35.00$1,225.00
2106.507GRANULAR EMBANKMENT (CV) (P)CU YD1,740$15.50$26,970.00$32.00$55,680.00$25.00$43,500.00
2106.507COMMON EMBANKMENT (CV) (P)CU YD220$15.50$3,410.00$30.00$6,600.00$20.00$4,400.00
2106.507SELECT GRANULAR EMBANKMENT MOD 7% (CV) (P)CU YD300$35.00$10,500.00$45.00$13,500.00$43.00$12,900.00
2118.507AGGREGATE SURFACING (CV) CLASS 5 (P)CU YD240$35.00$8,400.00$50.00$12,000.00$36.25$8,700.00
2211.507AGGREGATE BASE (CV) CLASS 5 (P)CU YD840$31.00$26,040.00$52.00$43,680.00$36.25$30,450.00
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON1,260$72.00$90,720.00$75.00$94,500.00$100.00$126,000.00
2401.503TYPE S (TL-4) 36" BARRIER CONC (3S52) (P)LIN FT152$150.00$22,800.00$180.00$27,360.00$249.00$37,848.00
2401.507STRUCTURAL CONCRETE (3B52) (P)CU YD86$950.00$81,700.00$1,600.00$137,600.00$990.00$85,140.00
2401.508REINFORCEMENT BARS (STAINLESS-75KSI) (P)POUND830$4.00$3,320.00$5.00$4,150.00$5.50$4,565.00
2401.508REINFORCEMENT BARS (EPOXY COATED) (P)POUND29,790$1.50$44,685.00$1.50$44,685.00$1.50$44,685.00
2401.601SLOPE PREPARATIONLUMP SUM1$5,000.00$5,000.00$10,000.00$10,000.00$15,000.00$15,000.00
2401.601STRUCTURE EXCAVATIONLUMP SUM1$20,000.00$20,000.00$60,000.00$60,000.00$17,543.00$17,543.00
2401.618BRIDGE SLAB CONCRETE (3YHPC-M) (P)SQ FT2,525$40.00$101,000.00$55.00$138,875.00$44.00$111,100.00
2402.502ELASTOMERIC BEARING PAD TYPE 1EACH14$125.00$1,750.00$150.00$2,100.00$200.00$2,800.00
2405.503PRESTRESSED CONCRETE BEAMS 22RB (P)LIN FT369$275.00$101,475.00$320.00$118,080.00$288.27$106,371.63
2406.504BRIDGE APPROACH PANELS (P)SQ YD210$250.00$52,500.00$240.00$50,400.00$376.00$78,960.00
2411.502CONCRETE FLUMEEACH2$1,500.00$3,000.00$2,500.00$5,000.00$2,105.00$4,210.00
2442.501REMOVE EXISTING BRIDGELUMP SUM1$100,000.00$100,000.00$42,500.00$42,500.00$127,750.00$127,750.00
2452.502PILE REDRIVINGEACH12$500.00$6,000.00$250.00$3,000.00$830.00$9,960.00
2452.601PILE HAMMER MOBILIZATIONLUMP SUM1$3,500.00$3,500.00$1,800.00$1,800.00$3,500.00$3,500.00
2452.602PILE PLACEMENTEACH12$3,250.00$39,000.00$1,100.00$13,200.00$830.00$9,960.00
2452.602ROCK SOCKETEACH12$3,250.00$39,000.00$6,000.00$72,000.00$5,507.00$66,084.00
2452.603PREBORING (EARTH)LIN FT96$433.00$41,568.00$850.00$81,600.00$850.00$81,600.00
2452.603STEEL H-PILING 10"LIN FT246$30.00$7,380.00$20.00$4,920.00$110.00$27,060.00
2502.501DRAINAGE SYSTEM TYPE (B910)LUMP SUM1$2,250.00$2,250.00$3,200.00$3,200.00$2,000.00$2,000.00
2511.504GEOTEXTILE FILTER TYPE 7SQ YD355$2.00$710.00$7.00$2,485.00$5.00$1,775.00
2511.507RANDOM RIPRAP CLASS IIICU YD216$50.00$10,800.00$80.00$17,280.00$75.00$16,200.00
2554.502END TREATMENT-TANGENT TERMINALEACH4$2,900.00$11,600.00$3,100.00$12,400.00$3,300.00$13,200.00
2554.503TRAFFIC BARRIER DESIGN TRANS TYPE 31LIN FT100$126.00$12,600.00$140.00$14,000.00$141.00$14,100.00
2554.503TRAFFIC BARRIER DESIGN TYPE 31LIN FT100$24.50$2,450.00$26.00$2,600.00$24.00$2,400.00
2563.601TRAFFIC CONTROLLUMP SUM0.45$10,000.00$4,500.00$15,000.00$6,750.00$3,500.00$1,575.00
2563.601PORTABLE SIGNAL SYSTEMLUMP SUM1$12,000.00$12,000.00$21,500.00$21,500.00$19,500.00$19,500.00
2563.601TRAFFIC CONTROLLUMP SUM0.55$10,000.00$5,500.00$15,000.00$8,250.00$3,500.00$1,925.00
2564.502OBJECT MARKER TYPE X4-5EACH4$150.00$600.00$160.00$640.00$150.00$600.00
2564.502OBJECT MARKER TYPE X4-4EACH4$200.00$800.00$210.00$840.00$200.00$800.00
2564.602INSTALL SIGNEACH3$125.00$375.00$130.00$390.00$125.00$375.00
2573.501EROSION CONTROL SUPERVISORLUMP SUM1$500.00$500.00$500.00$500.00$1,000.00$1,000.00
2573.501STABILIZED CONSTRUCTION EXITLUMP SUM1$2,000.00$2,000.00$1,500.00$1,500.00$25,000.00$25,000.00
2573.503FLOTATION SILT CURTAIN TYPE MOVING WATERLIN FT240$31.50$7,560.00$33.00$7,920.00$31.50$7,560.00
2573.503SILT FENCE; TYPE HILIN FT1,500$3.55$5,325.00$3.75$5,625.00$3.55$5,325.00
2574.508FERTILIZER TYPE 3POUND140$1.00$140.00$1.05$147.00$1.00$140.00
2575.504EROSION CONTROL BLANKETS CATEGORY 3NSQ YD1,750$1.58$2,765.00$1.65$2,887.50$1.58$2,765.00
2575.505SEEDINGACRE0.4$300.00$120.00$315.00$126.00$300.00$120.00
2575.508SEED MIXTURE 25-141POUND90$4.05$364.50$4.25$382.50$4.05$364.50
2575.523RAPID STABILIZATION METHOD 3M GALLON1.2$1,200.00$1,440.00$1,250.00$1,500.00$1,200.00$1,440.00
2582.5034" DBLE SOLID LINE PAINTLIN FT740$0.20$148.00$0.21$155.40$5.00$3,700.00
2582.5036" SOLID LINE PAINTLIN FT1,730$0.20$346.00$0.21$363.30$4.00$6,920.00
 Totals for project CP 0021-300205 (BR 285) $1,403,788.00 $1,654,000.00 $1,685,558.63
 
Contract Total:$1,403,788.00$1,654,000.00$1,685,558.63