Bid Abstract

CP 0012-275816 - CP 0012-275816 (Tied) - Bituminous Reclamation, P.M. Bit, Surface, Agg. ShouldersKGM Contractors, Inc Northland Constructors of Duluth, Inc. Ulland Brothers, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$20,000.00$20,000.00$49,947.65$49,947.65$66,755.73$66,755.73
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT1,027$2.50$2,567.50$2.00$2,054.00$1.75$1,797.25
2104.503REMOVE GUARDRAIL-PLATE BEAMLIN FT5,565$4.20$23,373.00$4.20$23,373.00$4.00$22,260.00
2104.503REMOVE PIPE CULVERTSLIN FT960$10.25$9,840.00$15.00$14,400.00$22.00$21,120.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD5,508$4.50$24,786.00$4.00$22,032.00$7.50$41,310.00
2105.504GEOTEXTILE FABRIC TYPE 6SQ YD2,268$3.75$8,505.00$3.00$6,804.00$2.50$5,670.00
2105.602TEMPORARY STREAM DIVERSION SYSTEMEACH4$2,800.00$11,200.00$2,200.00$8,800.00$7,600.00$30,400.00
2105.604GEOGRIDSQ YD1,050$3.77$3,958.50$4.00$4,200.00$2.50$2,625.00
2106.507GRANULAR EMBANKMENT (CV) (P)CU YD593$13.10$7,768.30$33.00$19,569.00$36.00$21,348.00
2118.509AGGREGATE SURFACING CLASS 5TON352$12.50$4,400.00$35.00$12,320.00$65.00$22,880.00
2118.609RECYCLED AGGREGATE SURFACINGTON3,176$14.90$47,322.40$26.00$82,576.00$24.00$76,224.00
2123.5100.5 CU YD SHOVELHOUR29$175.00$5,075.00$160.00$4,640.00$335.00$9,715.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR73$155.00$11,315.00$170.00$12,410.00$170.00$12,410.00
2123.510MOTOR GRADERHOUR73$195.00$14,235.00$230.00$16,790.00$175.00$12,775.00
2123.51012 CU YD TRUCKHOUR29$130.00$3,770.00$140.00$4,060.00$190.00$5,510.00
2123.5104.0 CU YD FRONT END LOADERHOUR29$195.00$5,655.00$160.00$4,640.00$185.00$5,365.00
2130.523WATERM GALLON110$33.00$3,630.00$54.00$5,940.00$44.00$4,840.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON6,373$1.05$6,691.65$1.05$6,691.65$1.00$6,373.00
2211.507AGGREGATE BASE (CV) CLASS 5 (P)CU YD728$30.00$21,840.00$34.00$24,752.00$46.00$33,488.00
2211.509AGGREGATE BASE CLASS 5TON750$14.55$10,912.50$16.00$12,000.00$17.00$12,750.00
2215.504FULL DEPTH RECLAMATIONSQ YD48,860$0.60$29,316.00$0.60$29,316.00$0.70$34,202.00
2232.504MILL BITUMINOUS SURFACE (3.0")SQ YD46,736$1.30$60,756.80$1.50$70,104.00$2.50$116,840.00
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON3,119$2.65$8,265.35$3.00$9,357.00$2.30$7,173.70
2360.509TYPE SP 9.5 WEARING COURSE MIX (3;C)TON12,174$55.20$672,004.80$65.00$791,310.00$65.70$799,831.80
2360.509TYPE SP 9.5 BIT MIXTURE FOR ENTRANCES (3,C)TON161$69.75$11,229.75$140.00$22,540.00$110.00$17,710.00
2411.507GRANULAR BACKFILL (CV) (P)CU YD1,197$15.35$18,373.95$33.00$39,501.00$34.00$40,698.00
2412.5026X4 PRECAST CONCRETE BOX CULV END SECTEACH2$7,000.00$14,000.00$10,300.00$20,600.00$7,200.00$14,400.00
2412.5036X4 PRECAST CONCRETE BOX CULVERTLIN FT48$615.00$29,520.00$560.00$26,880.00$740.00$35,520.00
2451.507GRANULAR BEDDING (CV) (P)CU YD505$27.25$13,761.25$43.00$21,715.00$50.00$25,250.00
2451.507STRUCTURE EXCAVATION CLASS E (P)CU YD6,154$9.00$55,386.00$12.00$73,848.00$23.00$141,542.00
2501.50230" RC PIPE APRONEACH2$1,125.00$2,250.00$1,935.00$3,870.00$1,570.00$3,140.00
2501.50224" GS PIPE APRONEACH2$520.00$1,040.00$360.00$720.00$440.00$880.00
2501.50218" RC PIPE APRONEACH8$860.00$6,880.00$1,100.00$8,800.00$880.00$7,040.00
2501.50221" SPAN GS PIPE-ARCH APRONEACH2$460.00$920.00$300.00$600.00$460.00$920.00
2501.50224" RC PIPE APRONEACH16$955.00$15,280.00$1,250.00$20,000.00$980.00$15,680.00
2501.50330" RC PIPE CULVERT DES 3006LIN FT68$124.00$8,432.00$103.00$7,004.00$130.00$8,840.00
2501.50324" CS PIPE CULVERTLIN FT30$60.00$1,800.00$40.00$1,200.00$60.00$1,800.00
2501.50318" RC PIPE CULVERT DES 3006LIN FT252$78.00$19,656.00$60.00$15,120.00$85.00$21,420.00
2501.50324" RC PIPE CULVERT DES 3006LIN FT384$90.00$34,560.00$72.00$27,648.00$93.00$35,712.00
2501.50321" SPAN CS PIPE-ARCH CULVERTLIN FT42$60.00$2,520.00$40.00$1,680.00$55.00$2,310.00
2501.602BULKHEAD CULVERTEACH1$1,500.00$1,500.00$685.00$685.00$1,330.00$1,330.00
2511.507RANDOM RIPRAP CLASS I (P)CU YD15$90.00$1,350.00$150.00$2,250.00$195.00$2,925.00
2511.507RANDOM RIPRAP CLASS IIICU YD347$79.00$27,413.00$48.00$16,656.00$88.00$30,536.00
2540.602MAIL BOX SUPPORTEACH43$158.00$6,794.00$160.00$6,880.00$150.00$6,450.00
2554.502END TREATMENT-ENERGY ABSORBING TERMINALEACH14$2,705.00$37,870.00$2,690.00$37,660.00$2,575.00$36,050.00
2554.503TRAFFIC BARRIER DESIGN B8307LIN FT4,865$31.00$150,815.00$30.00$145,950.00$29.50$143,517.50
2563.601TRAFFIC CONTROLLUMP SUM1$7,350.00$7,350.00$19,500.00$19,500.00$7,000.00$7,000.00
2573.503SEDIMENT CONTROL LOG TYPE STRAWLIN FT2,238$3.00$6,714.00$2.90$6,490.20$1.70$3,804.60
2573.503SILT FENCE; TYPE HILIN FT2,238$2.50$5,595.00$2.40$5,371.20$2.30$5,147.40
2575.504RAPID STABILIZATION METHOD 4SQ YD3,976$1.65$6,560.40$1.60$6,361.60$1.70$6,759.20
2580.503INTERIM PAVEMENT MARKINGLIN FT70,004$0.09$6,300.36$0.22$15,400.88$0.12$8,400.48
2582.5034" BROKEN LINE MULTI COMPLIN FT760$0.35$266.00$0.34$258.40$0.23$174.80
2582.5034" SOLID LINE PAINTLIN FT1,305$4.20$5,481.00$4.20$5,481.00$0.70$913.50
2582.5036" SOLID LINE MULTI COMPLIN FT37,772$0.46$17,375.12$0.48$18,130.56$0.30$11,331.60
2582.5034" SOLID LINE MULTI COMPLIN FT3,412$0.35$1,194.20$0.34$1,160.08$0.23$784.76
2582.5034" DBLE SOLID LINE MULTI COMPLIN FT15,415$0.67$10,328.05$0.68$10,482.20$0.46$7,090.90
2582.518PAVT MSSG PAINTSQ FT7.06$36.75$259.46$36.00$254.16$6.00$42.36
 Totals for project CP 0012-275816 $1,545,962.34 $1,828,783.58 $2,018,783.58
 
Contract Total:$1,545,962.34$1,828,783.58$2,018,783.58