Contract Bid Abstract

CP 0343-275035 (Tied) - CP 0343-275035 (Tied) - Reclaim & OverlayUlland Brothers, Inc. KGM Contractors, Inc Knife River Materials FKA Northstar Materials, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2016.601QUALITY MANAGEMENTLUMP SUM1$524.08$524.08$1,500.00$1,500.00$1,500.00$1,500.00
2021.501MOBILIZATIONLUMP SUM1$14,069.39$14,069.39$2,400.00$2,400.00$30,000.00$30,000.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT311$1.75$544.25$2.80$870.80$5.00$1,555.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD347$5.68$1,970.96$2.10$728.70$12.00$4,164.00
2118.509AGGREGATE SURFACING CLASS 5TON1,797$27.93$50,190.21$13.90$24,978.30$14.00$25,158.00
2123.510MOTOR GRADERHOUR66$156.58$10,334.28$197.00$13,002.00$145.00$9,570.00
2123.5100.5 CU YD SHOVELHOUR18$151.28$2,723.04$170.00$3,060.00$181.00$3,258.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR66$144.43$9,532.38$155.00$10,230.00$120.00$7,920.00
2130.523WATERM GALLON221$34.07$7,529.47$33.00$7,293.00$18.00$3,978.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON12,102$1.00$12,102.00$1.05$12,707.10$1.30$15,732.60
2211.509AGGREGATE BASE CLASS 5TON1,919$11.81$22,663.39$9.30$17,846.70$9.00$17,271.00
2211.604AGGREGATE BASE STABILIZATIONSQ YD60,508$0.35$21,177.80$0.46$27,833.68$0.59$35,699.72
2215.504FULL DEPTH RECLAMATIONSQ YD60,684$0.41$24,880.44$0.54$32,769.36$0.51$30,948.84
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON2,852$0.01$28.52$2.50$7,130.00$0.01$28.52
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON6,742$48.79$328,942.18$51.50$347,213.00$50.35$339,459.70
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON4,610$50.76$234,003.60$55.00$253,550.00$56.75$261,617.50
2540.602MAIL BOX SUPPORTEACH9$135.00$1,215.00$145.00$1,305.00$135.00$1,215.00
2563.601TRAFFIC CONTROLLUMP SUM1$2,000.00$2,000.00$1,300.00$1,300.00$2,800.00$2,800.00
2580.503INTERIM PAVEMENT MARKINGLIN FT14,400$0.12$1,728.00$0.09$1,296.00$0.35$5,040.00
2582.5034" SOLID LINE MULTI COMPLIN FT3,300$0.25$825.00$0.26$858.00$0.25$825.00
2582.50324" SOLID LINE PREF TAPE GR INLIN FT48$39.00$1,872.00$40.95$1,965.60$39.00$1,872.00
2582.5036" SOLID LINE MULTI COMPLIN FT38,898$0.34$13,225.32$0.36$14,003.28$0.34$13,225.32
2582.5034" BROKEN LINE MULTI COMPLIN FT3,900$0.25$975.00$0.26$1,014.00$0.25$975.00
 Totals for project CP 0343-275035 (Tied) $763,056.31 $784,854.52 $813,813.20
 
CP 0111-275034 (Tied) - CP 0111-275034, SAP 069-711-001 (Tied) CSAH 4 to CSAH 99Ulland Brothers, Inc. KGM Contractors, Inc Knife River Materials FKA Northstar Materials, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2016.601QUALITY MANAGEMENTLUMP SUM1$524.08$524.08$1,500.00$1,500.00$1,500.00$1,500.00
2021.501MOBILIZATIONLUMP SUM1$14,069.39$14,069.39$2,400.00$2,400.00$25,000.00$25,000.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT108$1.75$189.00$2.80$302.40$5.00$540.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD909$5.65$5,135.85$2.10$1,908.90$12.00$10,908.00
2118.509AGGREGATE SURFACING CLASS 5TON1,045$25.71$26,866.95$13.50$14,107.50$15.00$15,675.00
2123.5100.5 CU YD SHOVELHOUR18$151.28$2,723.04$170.00$3,060.00$181.00$3,258.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR66$144.43$9,532.38$155.00$10,230.00$120.00$7,920.00
2123.510MOTOR GRADERHOUR66$156.58$10,334.28$197.00$13,002.00$145.00$9,570.00
2130.523WATERM GALLON219$34.07$7,461.33$33.00$7,227.00$18.00$3,942.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON11,058$1.00$11,058.00$1.05$11,610.90$1.30$14,375.40
2211.509AGGREGATE BASE CLASS 5TON1,791$11.82$21,169.62$10.40$18,626.40$9.50$17,014.50
2211.604AGGREGATE BASE STABILIZATIONSQ YD55,290$0.35$19,351.50$0.46$25,433.40$0.59$32,621.10
2215.504FULL DEPTH RECLAMATIONSQ YD59,544$0.41$24,413.04$0.54$32,153.76$0.51$30,367.44
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON2,807$0.01$28.07$2.50$7,017.50$0.01$28.07
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON6,704$48.91$327,892.64$51.00$341,904.00$50.50$338,552.00
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON4,656$50.94$237,176.64$54.85$255,381.60$56.75$264,228.00
2540.602MAIL BOX SUPPORTEACH9$135.00$1,215.00$145.00$1,305.00$135.00$1,215.00
2563.601TRAFFIC CONTROLLUMP SUM1$2,000.00$2,000.00$2,520.00$2,520.00$1,200.00$1,200.00
2580.503INTERIM PAVEMENT MARKINGLIN FT15,046$0.12$1,805.52$0.09$1,354.14$0.35$5,266.10
2582.5034" SOLID LINE MULTI COMPLIN FT3,691$0.25$922.75$0.26$959.66$0.25$922.75
2582.50324" SOLID LINE PREF TAPE GR INLIN FT48$39.00$1,872.00$40.95$1,965.60$39.00$1,872.00
2582.5034" BROKEN LINE MULTI COMPLIN FT3,832$0.25$958.00$0.26$996.32$0.25$958.00
2582.5036" SOLID LINE MULTI COMPLIN FT38,278$0.34$13,014.52$0.36$13,780.08$0.34$13,014.52
2582.518PAVT MSSG PREF TAPE GR INSQ FT147.06$23.00$3,382.38$61.95$9,110.37$59.00$8,676.54
 Totals for project CP 0111-275034 (Tied) $743,095.98 $777,856.53 $808,624.42
 
CP 0341-319129 (Tied) - CP 0341-319129 (Tied) - Reclaim & OverlayUlland Brothers, Inc. KGM Contractors, Inc Knife River Materials FKA Northstar Materials, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2016.601QUALITY MANAGEMENTLUMP SUM1$524.08$524.08$1,200.00$1,200.00$800.00$800.00
2021.501MOBILIZATIONLUMP SUM1$14,069.39$14,069.39$2,400.00$2,400.00$26,000.00$26,000.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT24$1.75$42.00$2.70$64.80$5.00$120.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD348$8.37$2,912.76$2.10$730.80$12.00$4,176.00
2118.509AGGREGATE SURFACING CLASS 5TON945$25.71$24,295.95$11.95$11,292.75$16.00$15,120.00
2123.510MOTOR GRADERHOUR34$156.59$5,324.06$197.00$6,698.00$145.00$4,930.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR34$144.45$4,911.30$155.00$5,270.00$120.00$4,080.00
2123.5100.5 CU YD SHOVELHOUR9$151.28$1,361.52$170.00$1,530.00$181.00$1,629.00
2130.523WATERM GALLON114$34.07$3,883.98$33.00$3,762.00$18.00$2,052.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON5,347$1.00$5,347.00$1.05$5,614.35$1.30$6,951.10
2211.509AGGREGATE BASE CLASS 5TON2,140$9.07$19,409.80$9.10$19,474.00$11.00$23,540.00
2211.604AGGREGATE BASE STABILIZATIONSQ YD31,189$0.35$10,916.15$0.46$14,346.94$0.59$18,401.51
2215.504FULL DEPTH RECLAMATIONSQ YD31,189$0.41$12,787.49$0.54$16,842.06$0.51$15,906.39
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON1,471$0.01$14.71$2.50$3,677.50$0.01$14.71
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON2,430$49.22$119,604.60$52.00$126,360.00$58.10$141,183.00
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON3,599$47.30$170,232.70$49.00$176,351.00$51.90$186,788.10
2540.602MAIL BOX SUPPORTEACH26$135.00$3,510.00$145.00$3,770.00$135.00$3,510.00
2563.601TRAFFIC CONTROLLUMP SUM1$2,400.00$2,400.00$1,300.00$1,300.00$2,000.00$2,000.00
2580.503INTERIM PAVEMENT MARKINGLIN FT34,500$0.12$4,140.00$0.09$3,105.00$0.35$12,075.00
2582.5034" SOLID LINE MULTI COMPLIN FT2,600$0.25$650.00$0.26$676.00$0.25$650.00
2582.5036" SOLID LINE MULTI COMPLIN FT20,050$0.34$6,817.00$0.36$7,218.00$0.34$6,817.00
2582.5034" BROKEN LINE MULTI COMPLIN FT600$0.25$150.00$0.26$156.00$0.25$150.00
2582.5034" DBLE SOLID LINE MULTI COMPLIN FT7,025$0.50$3,512.50$0.53$3,723.25$0.50$3,512.50
 Totals for project CP 0341-319129 (Tied) $416,816.99 $415,562.45 $480,406.31
 
CP 6528-319130 (Tied) - CP 6528-319130 (Tied) - Reclaim & OverlayUlland Brothers, Inc. KGM Contractors, Inc Knife River Materials FKA Northstar Materials, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2016.601QUALITY MANAGEMENTLUMP SUM1$524.08$524.08$1,200.00$1,200.00$800.00$800.00
2021.501MOBILIZATIONLUMP SUM1$14,069.39$14,069.39$8,900.00$8,900.00$29,000.00$29,000.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT48$1.75$84.00$2.80$134.40$5.00$240.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD466$6.51$3,033.66$2.10$978.60$12.00$5,592.00
2105.504GEOTEXTILE FABRIC TYPE 6SQ YD1,708$1.78$3,040.24$2.75$4,697.00$3.00$5,124.00
2106.507EXCAVATION - COMMONCU YD1,689$6.61$11,164.29$8.00$13,512.00$20.00$33,780.00
2106.507SELECT GRANULAR EMBANKMENT MOD 7% (CV)CU YD1,267$12.59$15,951.53$8.75$11,086.25$20.00$25,340.00
2118.509AGGREGATE SURFACING CLASS 5TON889$25.71$22,856.19$12.10$10,756.90$15.00$13,335.00
2123.510MOTOR GRADERHOUR33$156.58$5,167.14$197.00$6,501.00$145.00$4,785.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR33$144.43$4,766.19$155.00$5,115.00$120.00$3,960.00
2123.5100.5 CU YD SHOVELHOUR9$151.28$1,361.52$170.00$1,530.00$181.00$1,629.00
2130.523WATERM GALLON109$34.07$3,713.63$33.00$3,597.00$18.00$1,962.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON5,120$1.00$5,120.00$1.05$5,376.00$1.30$6,656.00
2211.509AGGREGATE BASE CLASS 5TON1,660$8.16$13,545.60$9.00$14,940.00$10.50$17,430.00
2211.604AGGREGATE BASE STABILIZATIONSQ YD29,867$0.35$10,453.45$0.46$13,738.82$0.59$17,621.53
2215.504FULL DEPTH RECLAMATIONSQ YD29,867$0.41$12,245.47$0.54$16,128.18$0.51$15,232.17
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON1,408$0.01$14.08$2.50$3,520.00$0.01$14.08
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON3,388$46.28$156,796.64$49.90$169,061.20$51.80$175,498.40
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON2,283$48.22$110,086.26$52.80$120,542.40$59.20$135,153.60
2540.602MAIL BOX SUPPORTEACH16$135.00$2,160.00$145.00$2,320.00$135.00$2,160.00
2554.502END TREATMENT-ENERGY ABSORBING TERMINALEACH2$2,500.00$5,000.00$2,625.00$5,250.00$2,500.00$5,000.00
2554.503TRAFFIC BARRIER DESIGN B8307LIN FT200$19.25$3,850.00$20.20$4,040.00$19.25$3,850.00
2554.603RAISE GUARDRAILLIN FT660$10.25$6,765.00$10.75$7,095.00$10.25$6,765.00
2563.601TRAFFIC CONTROLLUMP SUM1$1,200.00$1,200.00$2,100.00$2,100.00$2,000.00$2,000.00
2575.504RAPID STABILIZATION METHOD 4SQ YD1,389$2.50$3,472.50$2.70$3,750.30$2.50$3,472.50
2580.503INTERIM PAVEMENT MARKINGLIN FT38,400$0.12$4,608.00$0.09$3,456.00$0.35$13,440.00
2582.5036" SOLID LINE MULTI COMPLIN FT19,200$0.34$6,528.00$0.36$6,912.00$0.34$6,528.00
2582.5034" DBLE SOLID LINE MULTI COMPLIN FT9,600$0.50$4,800.00$0.53$5,088.00$0.50$4,800.00
2582.50324" SOLID LINE PREF TAPE GR INLIN FT12$39.00$468.00$40.95$491.40$39.00$468.00
 Totals for project CP 6528-319130 (Tied) $432,844.86 $451,817.45 $541,636.28
 
CP 0341-387258 (Tied) - CP 0341-387258 (Tied) - Agg. Stabilization & OverlayUlland Brothers, Inc. KGM Contractors, Inc Knife River Materials FKA Northstar Materials, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$14,069.39$14,069.39$2,400.00$2,400.00$25,000.00$25,000.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT24$1.75$42.00$2.80$67.20$5.00$120.00
2118.509AGGREGATE SURFACING CLASS 5TON45$32.92$1,481.40$14.30$643.50$52.00$2,340.00
2123.510MOTOR GRADERHOUR4$156.53$626.12$197.00$788.00$145.00$580.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR4$144.39$577.56$155.00$620.00$120.00$480.00
2130.523WATERM GALLON11$34.12$375.32$33.00$363.00$18.00$198.00
2211.509AGGREGATE BASE CLASS 5TON182$14.13$2,571.66$9.30$1,692.60$15.00$2,730.00
2211.604AGGREGATE BASE STABILIZATIONSQ YD2,802$0.35$980.70$1.04$2,914.08$1.28$3,586.56
2215.504FULL DEPTH RECLAMATIONSQ YD624$0.41$255.84$1.07$667.68$1.65$1,029.60
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON142$0.01$1.42$2.50$355.00$0.01$1.42
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON294$72.14$21,209.16$53.00$15,582.00$72.50$21,315.00
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON419$70.19$29,409.61$49.90$20,908.10$66.50$27,863.50
2540.602MAIL BOX SUPPORTEACH1$135.00$135.00$145.00$145.00$135.00$135.00
2563.601TRAFFIC CONTROLLUMP SUM1$1,200.00$1,200.00$2,100.00$2,100.00$1,200.00$1,200.00
 Totals for project CP 0341-387258 (Tied) $72,935.18 $49,246.16 $86,579.08
 
CP 0099-275033 (Low) - CP 0099-275033, SAP 069-699-003 (Low) CSAH 16 to CSAH 100Ulland Brothers, Inc. KGM Contractors, Inc Knife River Materials FKA Northstar Materials, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2016.601QUALITY MANAGEMENT SPECIALLUMP SUM1$2,620.36$2,620.36$6,200.00$6,200.00$2,500.00$2,500.00
2016.601QUALITY MANAGEMENTLUMP SUM1$524.08$524.08$1,200.00$1,200.00$2,500.00$2,500.00
2021.501MOBILIZATIONLUMP SUM1$13,590.00$13,590.00$58,000.00$58,000.00$41,000.00$41,000.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT269$1.75$470.75$2.80$753.20$5.00$1,345.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD2,190$4.37$9,570.30$2.10$4,599.00$6.00$13,140.00
2105.504GEOTEXTILE FABRIC TYPE 6SQ YD935$1.94$1,813.90$2.75$2,571.25$3.00$2,805.00
2105.603OBLITERATE OLD ROADWAYLIN FT1,110$2.93$3,252.30$4.80$5,328.00$5.00$5,550.00
2106.507SELECT GRANULAR EMBANKMENT MOD 7% (CV)CU YD365$13.38$4,883.70$15.00$5,475.00$18.00$6,570.00
2106.507EXCAVATION - COMMONCU YD1,970$6.50$12,805.00$10.00$19,700.00$13.65$26,890.50
2118.507AGGREGATE SURFACING (CV) CLASS 5CU YD320$16.50$5,280.00$20.00$6,400.00$22.50$7,200.00
2118.509AGGREGATE SURFACING CLASS 5TON590$25.00$14,750.00$12.90$7,611.00$25.00$14,750.00
2123.5108 TON STEEL-WHEELED ROLLERHOUR110$144.43$15,887.30$155.00$17,050.00$120.00$13,200.00
2123.5100.5 CU YD SHOVELHOUR30$151.26$4,537.80$171.00$5,130.00$181.00$5,430.00
2123.510MOTOR GRADERHOUR110$156.58$17,223.80$197.00$21,670.00$145.00$15,950.00
2130.523WATERM GALLON365$34.07$12,435.55$33.00$12,045.00$18.00$6,570.00
2131.506CALCIUM CHLORIDE SOLUTIONGALLON17,125$1.00$17,125.00$1.05$17,981.25$1.30$22,262.50
2211.509AGGREGATE BASE CLASS 5TON3,159$9.50$30,010.50$9.45$29,852.55$9.00$28,431.00
2211.604AGGREGATE BASE STABILIZATIONSQ YD85,627$0.35$29,969.45$0.46$39,388.42$0.59$50,519.93
2215.504FULL DEPTH RECLAMATIONSQ YD85,627$0.41$35,107.07$0.54$46,238.58$0.51$43,669.77
2232.504MILL BITUMINOUS SURFACE (2.0")SQ YD76,634$0.29$22,223.86$0.95$72,802.30$1.05$80,465.70
2357.506BITUMINOUS MATERIAL FOR TACK COATGALLON4,895$0.01$48.95$2.50$12,237.50$0.01$48.95
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;C)TON10,843$50.45$547,029.35$51.00$552,993.00$50.15$543,776.45
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;C)TON10,350$52.51$543,478.50$55.80$577,530.00$55.35$572,872.50
2501.503INSTALL METAL CULVERTLIN FT100$18.25$1,825.00$25.00$2,500.00$62.00$6,200.00
2540.602MAIL BOX SUPPORTEACH37$135.00$4,995.00$141.75$5,244.75$135.00$4,995.00
2563.601TRAFFIC CONTROLLUMP SUM1$7,300.00$7,300.00$5,460.00$5,460.00$1,200.00$1,200.00
2573.503SILT FENCE; TYPE HILIN FT125$4.00$500.00$4.60$575.00$4.00$500.00
2575.504RAPID STABILIZATION METHOD 4SQ YD1,250$2.50$3,125.00$2.70$3,375.00$2.50$3,125.00
2575.523RAPID STABILIZATION METHOD 3M GALLON6$350.00$2,100.00$1,010.00$6,060.00$350.00$2,100.00
2580.503INTERIM PAVEMENT MARKINGLIN FT52,578$0.12$6,309.36$0.09$4,732.02$0.35$18,402.30
2582.5034" BROKEN LINE MULTI COMPLIN FT5,986$0.25$1,496.50$0.26$1,556.36$0.25$1,496.50
2582.5034" SOLID LINE MULTI COMPLIN FT6,998$0.25$1,749.50$0.26$1,819.48$0.25$1,749.50
2582.5036" SOLID LINE MULTI COMPLIN FT62,993$0.34$21,417.62$0.36$22,677.48$0.34$21,417.62
2582.5034" DBLE SOLID LINE MULTI COMPLIN FT2,271$0.50$1,135.50$0.53$1,203.63$0.50$1,135.50
 Totals for project CP 0099-275033 (Low) $1,396,591.00 $1,577,959.77 $1,569,768.72
 
Contract Total:$3,825,340.32$4,057,296.88$4,300,828.01