St Louis County Public Works Department

Welcome, Guest!
Log in | Employee Login | License
 

Bid Abstract

CP 0108-274367 (Tied) - CP 0108-274367, SAP 069-708-003 (BR 421) (Tied)Landwehr Construction, Inc. KGM Contractors, Inc Ulland Brothers, Inc. TNT Aggregates LLC Casper Construction, Inc. Hoover Construction Company Northland Constructors of Duluth, Inc. Rachel Contracting, Inc. Veit & Company, Inc. (Duluth) 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM0.71$5,100.00$3,621.00$9,500.00$6,745.00$22,000.00$15,620.00$30,000.00$21,300.00$7,500.00$5,325.00$15,400.00$10,934.00$10,801.30$7,668.92$26,692.23$18,951.48$18,445.90$13,096.59
2021.501MOBILIZATIONLUMP SUM0.29$5,100.00$1,479.00$9,500.00$2,755.00$22,000.00$6,380.00$30,000.00$8,700.00$7,500.00$2,175.00$15,400.00$4,466.00$10,801.30$3,132.38$26,692.23$7,740.75$18,445.90$5,349.31
2031.501FIELD OFFICE TYPE DEACH1$2,550.00$2,550.00$7,000.00$7,000.00$4,000.00$4,000.00$1,600.00$1,600.00$1,100.00$1,100.00$3,500.00$3,500.00$2,000.00$2,000.00$984.01$984.01$7,500.00$7,500.00
2101.501CLEARING & GRUBBINGLUMP SUM1$1,850.00$1,850.00$3,500.00$3,500.00$500.00$500.00$1,000.00$1,000.00$1,000.00$1,000.00$3,300.00$3,300.00$2,500.00$2,500.00$2,178.08$2,178.08$500.00$500.00
2105.601TEMPORARY STREAM DIVERSION SYSTEMLUMP SUM1$4,450.00$4,450.00$5,000.00$5,000.00$15,000.00$15,000.00$10,000.00$10,000.00$9,900.00$9,900.00$11,000.00$11,000.00$8,500.00$8,500.00$12,929.28$12,929.28$10,000.00$10,000.00
2105.601DEWATERINGLUMP SUM1$1,550.00$1,550.00$3,500.00$3,500.00$3,000.00$3,000.00$4,000.00$4,000.00$1,200.00$1,200.00$3,000.00$3,000.00$2,500.00$2,500.00$6,153.47$6,153.47$11,000.00$11,000.00
2105.604GEOTEXTILE FABRIC TYPE VISQ YD957$2.10$2,009.70$3.75$3,588.75$2.00$1,914.00$4.00$3,828.00$2.75$2,631.75$2.90$2,775.30$4.60$4,402.20$2.99$2,861.43$1.95$1,866.15
2105.607SELECT GRANULAR EMBANKMENT (CV) (P)CU YD1,214$21.50$26,101.00$12.90$15,660.60$17.50$21,245.00$19.00$23,066.00$29.50$35,813.00$20.00$24,280.00$21.00$25,494.00$29.45$35,752.30$23.05$27,982.70
2106.507EXCAVATION - COMMON (P)CU YD90$12.30$1,107.00$15.00$1,350.00$7.50$675.00$20.00$1,800.00$20.00$1,800.00$11.00$990.00$25.00$2,250.00$21.88$1,969.20$25.75$2,317.50
2106.507GRANULAR EMBANKMENT (CV) (P)CU YD406$21.50$8,729.00$12.90$5,237.40$17.50$7,105.00$20.00$8,120.00$31.50$12,789.00$14.00$5,684.00$18.00$7,308.00$21.71$8,814.26$22.50$9,135.00
2118.607AGGREGATE SURFACING (CV) CLASS 5 (P)CU YD450$33.00$14,850.00$23.00$10,350.00$26.00$11,700.00$19.00$8,550.00$33.00$14,850.00$25.00$11,250.00$35.00$15,750.00$30.49$13,720.50$35.75$16,087.50
2357.606BITUMINOUS MATERIAL FOR SHOULDER TACKGALLON42$22.00$924.00$7.00$294.00$28.00$1,176.00$12.00$504.00$20.00$840.00$20.00$840.00$5.00$210.00$23.15$972.30$21.95$921.90
2412.50212X9 PRECAST CONCRETE BOX CULV END SECTEACH2$22,180.00$44,360.00$23,300.00$46,600.00$19,500.00$39,000.00$20,000.00$40,000.00$22,000.00$44,000.00$24,350.00$48,700.00$24,600.00$49,200.00$21,289.36$42,578.72$18,525.00$37,050.00
2412.50312X9 PRECAST CONCRETE BOX CULVERTLIN FT54$1,140.00$61,560.00$1,210.00$65,340.00$1,250.00$67,500.00$1,225.00$66,150.00$1,285.00$69,390.00$1,215.00$65,610.00$1,300.00$70,200.00$1,073.86$57,988.44$1,200.00$64,800.00
2442.501REMOVE EXISTING BRIDGELUMP SUM1$5,950.00$5,950.00$5,000.00$5,000.00$5,000.00$5,000.00$6,000.00$6,000.00$9,900.00$9,900.00$10,000.00$10,000.00$9,900.00$9,900.00$9,745.37$9,745.37$35,100.00$35,100.00
2451.507COARSE AGGREGATE BEDDING (CV) (P)CU YD185$32.00$5,920.00$38.00$7,030.00$30.00$5,550.00$45.00$8,325.00$45.00$8,325.00$41.00$7,585.00$52.00$9,620.00$45.84$8,480.40$39.65$7,335.25
2501.502INSTALL CULVERT MARKEREACH4$170.00$680.00$155.00$620.00$145.00$580.00$145.00$580.00$145.00$580.00$150.00$600.00$150.00$600.00$167.86$671.44$159.60$638.40
2501.50253 SPAN CAS PIPE-ARCH APRONEACH4$1,605.00$6,420.00$1,765.00$7,060.00$1,100.00$4,400.00$1,500.00$6,000.00$1,450.00$5,800.00$2,350.00$9,400.00$1,630.00$6,520.00$1,382.43$5,529.72$2,990.00$11,960.00
2501.50353 SPAN CAS PIPE-ARCH CULVERTLIN FT132$120.00$15,840.00$160.00$21,120.00$85.00$11,220.00$100.00$13,200.00$89.00$11,748.00$133.00$17,556.00$103.00$13,596.00$92.73$12,240.36$137.50$18,150.00
2501.507CULVERT EXCAVATION CLASS U (P)CU YD1,198$10.50$12,579.00$10.65$12,758.70$10.00$11,980.00$10.00$11,980.00$6.00$7,188.00$10.00$11,980.00$15.00$17,970.00$14.17$16,975.66$15.45$18,509.10
2511.507RANDOM RIPRAP CLASS IIICU YD36$62.00$2,232.00$70.00$2,520.00$70.00$2,520.00$55.00$1,980.00$44.00$1,584.00$44.00$1,584.00$60.00$2,160.00$80.76$2,907.36$51.60$1,857.60
2563.601TRAFFIC CONTROLLUMP SUM0.29$1,500.00$435.00$3,300.00$957.00$2,400.00$696.00$2,400.00$696.00$2,400.00$696.00$2,500.00$725.00$2,500.00$725.00$2,778.38$805.73$2,000.00$580.00
2563.601TRAFFIC CONTROLLUMP SUM0.71$1,500.00$1,065.00$3,300.00$2,343.00$2,400.00$1,704.00$2,400.00$1,704.00$2,400.00$1,704.00$2,500.00$1,775.00$2,500.00$1,775.00$2,778.38$1,972.65$2,000.00$1,420.00
2573.501EROSION CONTROL SUPERVISORLUMP SUM1$1,250.00$1,250.00$1,000.00$1,000.00$250.00$250.00$500.00$500.00$1,200.00$1,200.00$1,700.00$1,700.00$750.00$750.00$1,297.99$1,297.99$1,400.00$1,400.00
2573.503SILT FENCE; TYPE HILIN FT1,025$3.30$3,382.50$3.30$3,382.50$3.00$3,075.00$3.00$3,075.00$3.00$3,075.00$3.10$3,177.50$3.10$3,177.50$3.53$3,618.25$3.35$3,433.75
2574.507COMMON TOPSOIL BORROWCU YD210$23.00$4,830.00$15.00$3,150.00$20.00$4,200.00$24.00$5,040.00$15.00$3,150.00$25.00$5,250.00$20.00$4,200.00$30.20$6,342.00$28.10$5,901.00
2574.508FERTILIZER TYPE 3POUND175$1.10$192.50$0.80$140.00$0.75$131.25$0.75$131.25$0.75$131.25$0.75$131.25$0.80$140.00$0.82$143.50$0.85$148.75
2575.504EROSION CONTROL BLANKETS CATEGORY 3NSQ YD2,400$1.80$4,320.00$2.05$4,920.00$1.65$3,960.00$1.65$3,960.00$1.65$3,960.00$1.70$4,080.00$1.70$4,080.00$1.84$4,416.00$1.80$4,320.00
2575.505SEEDINGACRE0.5$450.00$225.00$68.25$34.13$400.00$200.00$400.00$200.00$400.00$200.00$410.00$205.00$420.00$210.00$75.25$37.63$445.00$222.50
2575.508SEED MIXTURE 25-141POUND30$5.00$150.00$3.95$118.50$4.50$135.00$4.50$135.00$4.50$135.00$4.60$138.00$4.70$141.00$4.34$130.20$4.90$147.00
2575.523RAPID STABILIZATION METHOD 3M GALLON6$550.00$3,300.00$50.00$300.00$500.10$3,000.60$500.00$3,000.00$500.00$3,000.00$515.00$3,090.00$520.00$3,120.00$665.65$3,993.90$545.00$3,270.00
 Totals for project CP 0108-274367 (Tied) $243,911.70 $249,374.58 $253,416.85 $265,124.25 $265,190.00 $275,306.05 $279,800.00 $292,902.38 $322,000.00
 
Contract Total:$243,911.70$249,374.58$253,416.85$265,124.25$265,190.00$275,306.05$279,800.00$292,902.38$322,000.00