Bid Abstract

CP 0898-363599 - CP 0898-363599(Tied) Culvert ReplacementNorthland Constructors of Duluth, Inc. Rachel Contracting, Inc. Casper Construction, Inc. George Bougalis and Sons Co. Helmin Construction, Inc. KGM Contractors, Inc A+ Landscaping Ulland Brothers, Inc. Utility Systems of America, Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$4,000.00$4,000.00$7,728.84$7,728.84$6,000.30$6,000.30$6,287.00$6,287.00$5,900.00$5,900.00$6,550.00$6,550.00$6,000.00$6,000.00$8,600.00$8,600.00$16,000.00$16,000.00
2101.524CLEARINGTREE1$300.00$300.00$232.46$232.46$250.00$250.00$121.00$121.00$400.00$400.00$450.00$450.00$300.00$300.00$400.00$400.00$300.00$300.00
2101.524GRUBBINGTREE1$300.00$300.00$116.23$116.23$250.00$250.00$115.00$115.00$200.00$200.00$450.00$450.00$300.00$300.00$200.00$200.00$150.00$150.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT48$2.00$96.00$1.80$86.40$2.50$120.00$5.00$240.00$3.00$144.00$3.15$151.20$3.00$144.00$1.60$76.80$3.00$144.00
2104.503REMOVE PIPE CULVERTSLIN FT48$26.00$1,248.00$9.52$456.96$14.00$672.00$6.00$288.00$12.00$576.00$15.00$720.00$10.00$480.00$14.00$672.00$10.00$480.00
2104.504REMOVE BITUMINOUS PAVEMENTSQ YD72$7.00$504.00$3.99$287.28$5.75$414.00$4.00$288.00$8.00$576.00$4.15$298.80$4.50$324.00$8.20$590.40$4.00$288.00
2105.602TEMPORARY STREAM DIVERSION SYSTEMEACH1$1,000.00$1,000.00$1,649.05$1,649.05$4,100.00$4,100.00$3,369.00$3,369.00$4,000.00$4,000.00$4,000.00$4,000.00$500.00$500.00$5,000.00$5,000.00$8,500.00$8,500.00
2118.509AGGREGATE SURFACING CLASS 5TON5$140.00$700.00$65.93$329.65$37.00$185.00$54.00$270.00$20.00$100.00$15.30$76.50$25.00$125.00$132.00$660.00$35.00$175.00
2211.507AGGREGATE BASE (CV) CLASS 5 (P)CU YD26$45.00$1,170.00$38.77$1,008.02$45.00$1,170.00$32.00$832.00$30.00$780.00$38.00$988.00$32.00$832.00$75.00$1,950.00$30.00$780.00
2360.509TYPE SP 9.5 WEARING COURSE MIX (2;B)TON17$140.00$2,380.00$162.40$2,760.80$256.00$4,352.00$270.00$4,590.00$212.00$3,604.00$115.00$1,955.00$300.00$5,100.00$200.00$3,400.00$250.00$4,250.00
2401.507STRUCTURE EXCAVATION CLASS E (P)CU YD250$16.00$4,000.00$18.72$4,680.00$16.00$4,000.00$16.00$4,000.00$9.00$2,250.00$16.00$4,000.00$10.00$2,500.00$17.00$4,250.00$5.00$1,250.00
2451.507GRANULAR BEDDING (CV)CU YD120$34.00$4,080.00$23.62$2,834.40$22.00$2,640.00$23.00$2,760.00$45.00$5,400.00$36.00$4,320.00$28.00$3,360.00$33.00$3,960.00$25.00$3,000.00
2501.50236" RC PIPE APRONEACH2$2,000.00$4,000.00$1,557.05$3,114.10$1,600.00$3,200.00$1,512.00$3,024.00$1,500.00$3,000.00$1,850.00$3,700.00$3,500.00$7,000.00$1,900.00$3,800.00$3,500.00$7,000.00
2501.50336" RC PIPE CULVERT DES 3006LIN FT48$120.00$5,760.00$130.40$6,259.20$120.00$5,760.00$135.00$6,480.00$134.00$6,432.00$185.00$8,880.00$200.00$9,600.00$140.00$6,720.00$194.00$9,312.00
2511.507RANDOM RIPRAP CLASS IIICU YD19$60.00$1,140.00$109.86$2,087.34$98.00$1,862.00$63.00$1,197.00$50.00$950.00$80.00$1,520.00$75.00$1,425.00$105.00$1,995.00$60.00$1,140.00
2563.601TRAFFIC CONTROLLUMP SUM1$3,200.00$3,200.00$2,784.01$2,784.01$2,850.00$2,850.00$3,516.00$3,516.00$5,000.00$5,000.00$3,800.00$3,800.00$3,600.00$3,600.00$2,400.00$2,400.00$3,000.00$3,000.00
2573.501EROSION CONTROL SUPERVISORLUMP SUM1$500.00$500.00$1.14$1.14$250.00$250.00$1,264.00$1,264.00$2,000.00$2,000.00$655.00$655.00$500.00$500.00$1,500.00$1,500.00$500.00$500.00
2573.503SEDIMENT CONTROL LOG TYPE STRAWLIN FT60$4.50$270.00$7.81$468.60$4.25$255.00$3.00$180.00$3.00$180.00$4.50$270.00$4.00$240.00$4.10$246.00$5.00$300.00
2575.504RAPID STABILIZATION METHOD 4SQ YD87$2.60$226.20$2.90$252.30$2.10$182.70$2.00$174.00$5.00$435.00$2.30$200.10$2.20$191.40$2.10$182.70$3.00$261.00
2582.5034" DBLE SOLID LINE PAINTLIN FT27$3.00$81.00$2.32$62.64$10.00$270.00$7.00$189.00$2.50$67.50$2.10$56.70$15.00$405.00$2.00$54.00$15.00$405.00
2582.5036" SOLID LINE PAINTLIN FT54$2.00$108.00$1.28$69.12$8.00$432.00$5.00$270.00$1.50$81.00$1.05$56.70$10.00$540.00$1.10$59.40$12.00$648.00
 Totals for project CP 0898-363599 $35,063.20 $37,268.54 $39,215.00 $39,454.00 $42,075.50 $43,098.00 $43,466.40 $46,716.30 $57,883.00
 
Contract Total:$35,063.20$37,268.54$39,215.00$39,454.00$42,075.50$43,098.00$43,466.40$46,716.30$57,883.00