St Louis County Public Works Department

Welcome, Guest!
Log in | Employee Login | License
 

Contract Bid Abstract

CP 0137-317611, SAP 069-737-003 - CP 0137-317611, SAP 069-737-003 (BR 550)KGM Contractors, Inc Casper Construction, Inc. Landwehr Construction, Inc. Ulland Brothers, Inc. George Bougalis and Sons Co. Hoover Construction Company A+ Landscaping 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM0.58$29,000.00$16,820.00$25,879.25$15,009.97$25,000.00$14,500.00$33,570.75$19,471.04$55,000.00$31,900.00$37,000.00$21,460.00$45,000.00$26,100.00
2021.501MOBILIZATIONLUMP SUM0.42$29,000.00$12,180.00$25,879.25$10,869.29$25,000.00$10,500.00$33,570.75$14,099.72$55,000.00$23,100.00$37,000.00$15,540.00$45,000.00$18,900.00
2031.501FIELD OFFICE TYPE DEACH1$5,000.00$5,000.00$1,000.00$1,000.00$8,500.00$8,500.00$3,000.00$3,000.00$4,000.00$4,000.00$5,555.00$5,555.00$10,000.00$10,000.00
2101.511CLEARING & GRUBBINGLUMP SUM1$3,500.00$3,500.00$350.00$350.00$1,150.00$1,150.00$4,500.00$4,500.00$1,500.00$1,500.00$1,250.00$1,250.00$5,000.00$5,000.00
2104.501REMOVE GUARDRAIL-PLATE BEAMLIN FT461$5.00$2,305.00$11.50$5,301.50$11.00$5,071.00$20.25$9,335.25$5.00$2,305.00$21.00$9,681.00$5.00$2,305.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)LIN FT48$3.00$144.00$2.60$124.80$3.25$156.00$5.00$240.00$6.00$288.00$10.00$480.00$3.00$144.00
2104.523SALVAGE SIGNEACH11$65.00$715.00$25.00$275.00$31.00$341.00$25.00$275.00$80.00$880.00$30.00$330.00$125.00$1,375.00
2104.523SALVAGE HYDRANTEACH2$200.00$400.00$450.00$900.00$570.00$1,140.00$1,000.00$2,000.00$1,000.00$2,000.00$950.00$1,900.00$800.00$1,600.00
2105.601DEWATERINGLUMP SUM1$2,500.00$2,500.00$4,000.00$4,000.00$11,050.00$11,050.00$10,000.00$10,000.00$5,000.00$5,000.00$4,000.00$4,000.00$10,000.00$10,000.00
2105.601TEMPORARY STREAM DIVERSION SYSTEMLUMP SUM1$7,700.00$7,700.00$13,000.00$13,000.00$9,750.00$9,750.00$25,000.00$25,000.00$28,000.00$28,000.00$35,500.00$35,500.00$10,000.00$10,000.00
2105.604GEOTEXTILE FABRIC TYPE VISQ YD1,400$3.00$4,200.00$2.50$3,500.00$2.00$2,800.00$2.00$2,800.00$2.00$2,800.00$2.75$3,850.00$2.00$2,800.00
2105.607GRANULAR EMBANKMENT (CV) (P)CU YD1,071$11.50$12,316.50$18.25$19,545.75$16.60$17,778.60$15.00$16,065.00$22.00$23,562.00$18.00$19,278.00$28.00$29,988.00
2106.501EXCAVATION - COMMON (P)CU YD1,122$16.20$18,176.40$6.75$7,573.50$14.00$15,708.00$14.00$15,708.00$19.00$21,318.00$13.00$14,586.00$15.00$16,830.00
2106.522SELECT GRANULAR EMBANKMENT MOD 7% (CV) (P)CU YD1,720$12.50$21,500.00$18.25$31,390.00$16.50$28,380.00$20.00$34,400.00$22.00$37,840.00$16.00$27,520.00$28.00$48,160.00
2118.607AGGREGATE SURFACING (CV) CLASS 5 (P)CU YD10$50.00$500.00$53.00$530.00$36.00$360.00$100.00$1,000.00$80.00$800.00$24.00$240.00$35.00$350.00
2211.503AGGREGATE BASE (CV) CLASS 5 (P)CU YD1,068$19.00$20,292.00$24.75$26,433.00$22.00$23,496.00$28.00$29,904.00$32.00$34,176.00$16.50$17,622.00$35.00$37,380.00
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLON162$2.40$388.80$3.00$486.00$3.35$542.70$3.00$486.00$3.10$502.20$5.00$810.00$4.00$648.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (3;C)TON1,165$68.50$79,802.50$71.00$82,715.00$79.50$92,617.50$71.00$82,715.00$71.50$83,297.50$75.00$87,375.00$76.00$88,540.00
2412.51116X8 PRECAST CONCRETE BOX CULVERTLIN FT96$1,300.00$124,800.00$1,260.00$120,960.00$1,160.00$111,360.00$1,150.00$110,400.00$1,155.00$110,880.00$1,285.00$123,360.00$1,400.00$134,400.00
2412.51116X9 PRECAST CONCRETE BOX CULVERTLIN FT96$1,400.00$134,400.00$1,320.00$126,720.00$1,215.00$116,640.00$1,190.00$114,240.00$1,155.00$110,880.00$1,330.00$127,680.00$1,500.00$144,000.00
2412.51216X8 PRECAST CONCRETE BOX CULV END SECEACH2$23,500.00$47,000.00$26,000.00$52,000.00$22,900.00$45,800.00$24,000.00$48,000.00$23,000.00$46,000.00$27,000.00$54,000.00$30,000.00$60,000.00
2412.51216X9 PRECAST CONCRETE BOX CULV END SECEACH2$25,500.00$51,000.00$28,750.00$57,500.00$25,350.00$50,700.00$25,000.00$50,000.00$26,000.00$52,000.00$30,000.00$60,000.00$35,000.00$70,000.00
2442.501REMOVE EXISTING BRIDGELUMP SUM1$7,250.00$7,250.00$10,500.00$10,500.00$14,200.00$14,200.00$24,000.00$24,000.00$8,800.00$8,800.00$23,500.00$23,500.00$30,000.00$30,000.00
2451.503GRANULAR BACKFILL (CV) (P)CU YD1,425$11.50$16,387.50$18.60$26,505.00$18.70$26,647.50$24.00$34,200.00$22.00$31,350.00$28.00$39,900.00$25.00$35,625.00
2451.515COARSE AGGREGATE BEDDING (CV) (P)CU YD710$32.00$22,720.00$33.50$23,785.00$39.00$27,690.00$36.00$25,560.00$40.00$28,400.00$37.50$26,625.00$35.00$24,850.00
2501.501CULVERT EXCAVATION CLASS U (P)CU YD1,135$10.50$11,917.50$4.50$5,107.50$15.80$17,933.00$10.00$11,350.00$19.00$21,565.00$25.00$28,375.00$15.00$17,025.00
2511.501RANDOM RIPRAP CLASS IIICU YD100$60.00$6,000.00$40.00$4,000.00$54.00$5,400.00$60.00$6,000.00$75.00$7,500.00$60.00$6,000.00$75.00$7,500.00
2563.601TRAFFIC CONTROLLUMP SUM0.58$4,500.00$2,610.00$4,400.00$2,552.00$4,900.00$2,842.00$4,200.00$2,436.00$4,600.00$2,668.00$5,000.00$2,900.00$5,000.00$2,900.00
2563.601TRAFFIC CONTROLLUMP SUM0.42$4,500.00$1,890.00$4,400.00$1,848.00$4,900.00$2,058.00$4,200.00$1,764.00$4,600.00$1,932.00$5,000.00$2,100.00$5,000.00$2,100.00
2564.536INSTALL SIGN PANEL TYPE CEACH11$127.00$1,397.00$125.00$1,375.00$12.50$137.50$150.00$1,650.00$126.00$1,386.00$130.00$1,430.00$250.00$2,750.00
2573.502SILT FENCE; TYPE HILIN FT3,530$3.95$13,943.50$3.00$10,590.00$3.30$11,649.00$4.50$15,885.00$3.10$10,943.00$3.15$11,119.50$4.00$14,120.00
2573.535STABILIZED CONSTRUCTION EXITLUMP SUM1$1,000.00$1,000.00$1,250.00$1,250.00$1,780.00$1,780.00$1,200.00$1,200.00$1,000.00$1,000.00$2,000.00$2,000.00$1,500.00$1,500.00
2573.550EROSION CONTROL SUPERVISORLUMP SUM1$750.00$750.00$1,000.00$1,000.00$1,800.00$1,800.00$3,000.00$3,000.00$4,200.00$4,200.00$600.00$600.00$500.00$500.00
2574.508FERTILIZER TYPE 3POUND578$1.05$606.90$0.65$375.70$1.00$578.00$5.00$2,890.00$0.70$404.60$0.70$404.60$1.00$578.00
2574.525COMMON TOPSOIL BORROWCU YD666$17.00$11,322.00$30.00$19,980.00$25.50$16,983.00$8.00$5,328.00$28.00$18,648.00$38.00$25,308.00$35.00$23,310.00
2575.502SEED MIXTURE 36-311POUND116$36.50$4,234.00$10.00$1,160.00$47.00$5,452.00$50.00$5,800.00$10.25$1,189.00$10.50$1,218.00$28.00$3,248.00
2575.523EROSION CONTROL BLANKETS CATEGORY 3NSQ YD7,990$1.60$12,784.00$1.25$9,987.50$2.50$19,975.00$3.00$23,970.00$1.35$10,786.50$1.30$10,387.00$2.00$15,980.00
2575.571RAPID STABILIZATION METHOD 3M GALLON3.9$50.00$195.00$700.00$2,730.00$725.00$2,827.50$1,250.00$4,875.00$750.00$2,925.00$735.00$2,866.50$1,100.00$4,290.00
2575.605SEEDINGACRE1.65$80.00$132.00$450.00$742.50$560.00$924.00$2,500.00$4,125.00$480.00$792.00$500.00$825.00$500.00$825.00
2582.5024" SOLID LINE EPOXYLIN FT1,850$1.50$2,775.00$1.40$2,590.00$1.50$2,775.00$1.40$2,590.00$2.50$4,625.00$1.50$2,775.00$2.50$4,625.00
2582.5026" SOLID LINE EPOXYLIN FT1,850$1.55$2,867.50$1.48$2,738.00$1.70$3,145.00$1.48$2,738.00$2.60$4,810.00$1.55$2,867.50$2.50$4,625.00
 Totals for project CP 0137-317611, SAP 069-737-003 $686,422.10 $709,000.01 $733,137.30 $773,000.01 $786,952.80 $823,218.10 $914,871.00
 
Contract Total:$686,422.10$709,000.01$733,137.30$773,000.01$786,952.80$823,218.10$914,871.00